NOGRR170

Summary

Title Alignment with NPRR824, Alignment of EEA Level 3 with NERC Reliability Standards EOP-011-1 and BAL-001-2
Next Group
Next Step
Status Approved on 06/28/2017
Effective Dates
07/01/2017

Action

Date Gov Body Action Taken Next Steps
06/28/2017 TAC Approved
06/08/2017 ROS Recommended for Approval Revision Request Consideration
05/18/2017 OWG Recommended for Approval ROS for consideration
04/20/2017 OWG Recommended for Approval OWG for Impact Analysis review

Voting Record

Date Gov Body Motion Result
06/28/2017 TAC To approve NOGRR170 as recommended by ROS in the 6/8/17 ROS Report Passed
06/08/2017 ROS To recommend approval of NOGRR170 as recommended by OWG in the 5/18/17 OWG Report. Passed
05/18/2017 OWG To endorse and forward to ROS the 4/20/17 OWG Report and Impact Analysis for NOGRR170 Passed
04/20/2017 OWG To recommend approval of NOGRR170 as submitted Passed

Background

Status: Approved
Date Posted: Mar 29, 2017
Sponsor: ERCOT
Urgent: No
Sections: 4.5.3 and 4.5.3.1
Description: This Nodal Operating Guide Revision Request (NOGRR) revises the Nodal Operating Guide (NOG) to be consistent with NPRR824 language relating to North American Reliability Corporation (NERC) Reliability Standards EOP-011-1, Emergency Operations, and BAL-001-2, Real Power Balancing Control Performance. Pursuant to paragraph (5) of Section 1.3.1, Introduction, this NOGRR does not modify Section 4.5.3.3, EEA Levels. An Alignment NOGRR will be posted upon ERCOT Board approval of NPRR824 to maintain alignment of Protocol Section 6.5.9.4.2, EEA Levels, with NOG Section 4.5.3.3.
Reason: Regulatory requirements