To approve NOGRR240 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization
to table NOGRR240 and refer the issue to the Dynamics Working Group (DWG), Operations Working Group (OWG), and Planning Working Group (PLWG)
Passed
Background
Status:
Approved
Date Posted:
Feb 16, 2022
Sponsor:
ERCOT
Urgent:
No
Sections:
2.6.3 (new) and 2.10 (new)
Description:
This Nodal Operating Guide Revision Request (NOGRR) establishes frequency and voltage ride-through requirements for new Direct Current Ties (DC Ties) interconnecting to the ERCOT System after January 1, 2021, and certain DC Ties that will be modified.
Reason:
Other: Addresses future potential operational issues associated with DC Ties