Summary

Title Related to NPRR1161, Clarify AVR Notification Requirements for IRRs
Next Group
Next Step
Status Approved on 07/20/2023

Action

Date Gov Body Action Taken Next Steps
07/20/2023 PUCT Approved
06/20/2023 BOARD Recommended for Approval Revision Request Consideration
05/23/2023 TAC Recommended for Approval Revision Request Consideration
04/06/2023 ROS Recommended for Approval Revision Request Consideration
03/02/2023 ROS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
07/20/2023 PUCT to approve NOGRR246 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization Passed
06/20/2023 BOARD to recommend approval of NOGRR246 as recommended by TAC in the 5/23/23 TAC Report Passed
05/23/2023 TAC to recommend approval of NOGRR246 as recommended by ROS in the 4/6/23 ROS Report Passed
04/06/2023 ROS to endorse and forward to TAC the 3/2/23 ROS Report as revised by ROS and the 2/7/23 Impact Analysis for NOGRR246 Passed
03/02/2023 ROS to recommend approval of NOGRR246 as submitted Passed

Background

Status: Approved
Date Posted: Feb 7, 2023
Sponsor: ERCOT
Urgent: No
Sections: 2.2.5, 2.7.3.4
Description: This Nodal Operating Guide Revision Request (NOGRR) clarifies that Intermittent Renewable Resources (IRRs), who remain synchronized to the ERCOT System but are not able to provide reactive power when not providing real power, do not have to notify ERCOT other than the Real-Time telemetered status.
Reason: Addresses current operational issues