Summary

Title Related to NPRR1244, Clarification of Controllable Load Resource Primary Frequency Response Responsibilities
Next Group PUCT
Next Step Revision Request Consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
10/10/2024 BOARD Recommended for Approval Revision Request Consideration
09/19/2024 TAC Recommended for Approval Revision Request Consideration
09/09/2024 ROS Recommended for Approval Revision Request Consideration
08/01/2024 ROS Recommended for Approval Impact Analysis Consideration
05/02/2024 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
10/10/2024 BOARD to recommend approval of NOGRR263 as recommended by TAC in the 9/19/24 TAC Report Passed
09/19/2024 TAC to recommend approval of NOGRR263 as recommended by ROS in the 9/9/24 ROS Report; and the 9/13/24 Revised Impact Analysis Passed
09/09/2024 ROS to endorse and forward to TAC the 8/1/24 ROS Report as revised by ROS and the 9/6/24 Impact Analysis for NOGRR263 Passed
08/01/2024 ROS to recommend approval of NOGRR263 as amended by the 7/22/24 Priority Power comments Passed
05/02/2024 ROS to table NOGRR263 and refer the issue to the Performance, Disturbance, Compliance (PDCWG) Working Group Passed

Background

Status: Pending
Date Posted: Apr 10, 2024
Sponsor: Priority Power
Urgent: No
Sections: 2.2.8, 8J
Description: This Nodal Operating Guide Revision Request (NOGRR) clarifies that a Controllable Load Resource is only required to provide Primary Frequency Response when it is providing an Ancillary Service that requires the Controllable Load Resource to be capable of providing Primary Frequency Response.
Reason: General system and/or process improvement(s)