NOGRR267
Summary
Title | Related to NPRR1240, Access to Transmission Planning Information |
---|---|
Next Group | |
Next Step | |
Status | Approved on 01/16/2025 |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
01/16/2025 | PUCT | Approved | |
12/03/2024 | BOARD | Recommended for Approval | Revision Request Consideration |
11/20/2024 | TAC | Recommended for Approval | Revision Request Consideration |
10/30/2024 | TAC | Deferred/Tabled | Revision Request Consideration |
10/03/2024 | ROS | Recommended for Approval | Revision Request Consideration |
09/09/2024 | ROS | Recommended for Approval | Impact Analysis Consideration |
08/01/2024 | ROS | Deferred/Tabled | Language Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
01/16/2025 | PUCT | to approve NOGRR267 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization | Passed |
12/03/2024 | BOARD | to recommend approval of NOGRR267 as recommended by TAC in the 11/20/24 TAC Report | Passed |
11/20/2024 | TAC | to recommend approval of NOGRR267 as recommended by ROS in the 10/3/24 ROS Report | Passed |
10/30/2024 | TAC | to table NOGRR267 | Passed |
10/03/2024 | ROS | to endorse and forward to TAC the 9/9/24 ROS Report and 7/2/24 Impact Analysis for NOGRR267 | Passed |
09/09/2024 | ROS | to recommend approval of NOGRR267 as submitted | Passed |
08/01/2024 | ROS | to table NOGRR267 | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Jul 2, 2024 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 9.2.3 and 9.3.1 |
Description: | This Nodal Operating Guide Revision Request (NOGRR) moves from the Market Information System (MIS) Secure Area to the public ERCOT website reports that do not contain ERCOT Critical Energy Infrastructure Information (ECEII). ERCOT Staff analyzed reports in the MIS Secure Area, along with existing Protocols for posting requirements, and identified no ongoing basis for holding in the MIS Secure Area reports determined to contain only Transmission planning information for a market audience, consisting of percentages of Transmission Outage totals by scheduling and type, and monthly reports that show the rates at which solutions converged in the State Estimator application and not ECEII. |
Reason: | General system and/or process improvement(s) |
Key Documents
Jul 2, 2024 - docx - 51.2 KB
Jul 2, 2024 - docx - 31.5 KB
Aug 6, 2024 - xls - 137.5 KB
Aug 6, 2024 - docx - 52.9 KB
Sep 12, 2024 - xls - 137.5 KB
Sep 12, 2024 - docx - 53 KB
Oct 8, 2024 - xls - 137.5 KB
Oct 8, 2024 - docx - 53.3 KB
Nov 4, 2024 - xls - 144 KB
Nov 4, 2024 - docx - 61.9 KB
Nov 21, 2024 - xls - 144 KB
Nov 21, 2024 - docx - 61.8 KB
Dec 5, 2024 - docx - 62.4 KB
Jan 22, 2025 - docx - 62.4 KB