NPRR048
Summary
Title | Revised Wording of Opportunity Outages for Transmission Facilities |
---|---|
Next Group | |
Next Step | |
Status | Approved on 07/17/2007 |
Effective Dates |
12/01/2010
or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (08/01/07 Nodal Protocols Library) |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
07/17/2007 | BOARD | Approved | |
06/28/2007 | TAC | Recommended for Approval | Board consideration of this NPRR and its IA |
06/12/2007 | PRS | Recommended for Approval | Review of B1G1 Impact Analysis |
03/22/2007 | PRS | Recommended for Approval | PRS consideration of the Impact Analysis |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
07/17/2007 | BOARD | To approve this NPRR as recommended by TAC. | Passed |
06/28/2007 | TAC | To recommend approval of this NPRR and its IA as recommended by PRS. | Passed |
06/12/2007 | PRS | To recommend approval of B1G1 Impact Analysis | Passed |
03/22/2007 | PRS | Recommend for approval as revised by ERCOT Staff comments | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Mar 8, 2007 |
Sponsor: | Trip Doggett on behalf of TPTF |
Urgent: | No |
Sections: | 2.1, 3.1.6.8 |
Description: | The proposed Opportunity Outages rewording will allow ERCOT to grant a TSP permission to work on TSP-owned equipment that can only be maintained when a Resource is off-line for a Forced, Planned or Maintenance Outage. |
Reason: | This NPRR will give Transmission Operators enhanced ability to maintain, replace or upgrade transmission facilities that connect a Resource to the interconnected ERCOT system. |
Key Documents
Mar 8, 2007 - doc - 87.5 KB
Mar 14, 2007 - doc - 82 KB
Mar 23, 2007 - doc - 127 KB
Jun 15, 2007 - doc - 55.5 KB
Jun 14, 2007 - doc - 201.5 KB
Jul 2, 2007 - doc - 329 KB
Jul 20, 2007 - doc - 451 KB
Jan 2, 2008 - xls - 75 KB