NPRR048

Summary

Title Revised Wording of Opportunity Outages for Transmission Facilities
Next Group
Next Step
Status Approved on 07/17/2007
Effective Dates
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (08/01/07 Nodal Protocols Library)

Action

Date Gov Body Action Taken Next Steps
07/17/2007 BOARD Approved
06/28/2007 TAC Recommended for Approval Board consideration of this NPRR and its IA
06/12/2007 PRS Recommended for Approval Review of B1G1 Impact Analysis
03/22/2007 PRS Recommended for Approval PRS consideration of the Impact Analysis

Voting Record

Date Gov Body Motion Result
07/17/2007 BOARD To approve this NPRR as recommended by TAC. Passed
06/28/2007 TAC To recommend approval of this NPRR and its IA as recommended by PRS. Passed
06/12/2007 PRS To recommend approval of B1G1 Impact Analysis Passed
03/22/2007 PRS Recommend for approval as revised by ERCOT Staff comments Passed

Background

Status: Approved
Date Posted: Mar 8, 2007
Sponsor: Trip Doggett on behalf of TPTF
Urgent: No
Sections: 2.1, 3.1.6.8
Description: The proposed Opportunity Outages rewording will allow ERCOT to grant a TSP permission to work on TSP-owned equipment that can only be maintained when a Resource is off-line for a Forced, Planned or Maintenance Outage.
Reason: This NPRR will give Transmission Operators enhanced ability to maintain, replace or upgrade transmission facilities that connect a Resource to the interconnected ERCOT system.