Background
Status:
Approved
Date Posted:
Mar 8, 2007
Sponsor:
Trip Doggett on behalf of TPTF
Urgent:
No
Sections:
2.1, 3.1.6.8
Description:
The proposed Opportunity Outages rewording will allow ERCOT to grant a TSP permission to work on TSP-owned equipment that can only be maintained when a Resource is off-line for a Forced, Planned or Maintenance Outage.
Reason:
This NPRR will give Transmission Operators enhanced ability to maintain, replace or upgrade transmission facilities that connect a Resource to the interconnected ERCOT system.