To recommend approval of NPRR057 as recommended by TPTF.
Passed
Background
Status:
Approved
Date Posted:
Apr 9, 2007
Sponsor:
TPTF
Urgent:
No
Sections:
3.2, Analysis of Long-Term Resource Adequacy; 3.2.1, Calculation of Aggregate Generating Capacity; 3.2.2, Long-Term Demand Forecasts; 3.2.3, System Adequacy Report; 3.2.4, Statement of Opportunities (New); 3.12, Load Forecasting; 3.12.1, Mid-Term Load Forecast; 3.12.2, Long-Term Load Forecast 3.13, Renewable Production Potential Forecasts; 4.2.3, Posting Forecasted ERCOT System Conditions.
Description:
This NPRR implements posting requirements outlined in new P.U.C. Subst. R. 25.505, Resource Adequacy in the Electric Reliability of Texas Power Region.
Reason:
Compliance with PUCT Order in Project No. 31972, Rulemaking Concerning Resource Adequacy and Market Power in the Electric Reliability Council of Texas Power Region. This NPRR reflects only a first set of changes to implement the rule provisions adopted under P.U.C. Project No. 31972. Additional NPRRs will be proposed to implement other rule provisions resulting from P.U.C. Project No. 31972.