NPRR076

Summary

Title Synchronization of Emergency Electric Curtailment Plan (EECP) Event Realignment
Next Group
Next Step
Status Approved on 12/11/2007
Effective Dates
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (01/01/08 Nodal Protocols Library)

Voting Record

Date Gov Body Motion Result
12/11/2007 BOARD Approve NPRR076 as recommended by TAC Passed
11/29/2007 TAC Recommend approval of NPRR076 and to instruct ERCOT to design the Nodal system in such a way to allow the RDF to be reduced to zero. Passed
11/15/2007 PRS To forward the Recommendation Report and IA to TAC. Passed
10/18/2007 PRS Recommend approval of NPRR076 as revised by DSWG comments. Passed
09/20/2007 PRS To table further consideration of NPRR076 until the October PRS meeting to allow for additional comments. Passed
08/23/2007 PRS
07/19/2007 PRS Remand NPRR076 to WMS and direct that the Demand Side Working Group (DSWG) further review the Load Resource selection process in Section 6.5.9.4.1, EECP Steps. Passed

Background

Status: Approved
Date Posted: Jul 2, 2007
Sponsor: TPTF
Urgent: No
Sections: 2.1, 2.2, 6.5.7.5, 6.5.9.4, 6.5.9.4.1 (new), 6.5.9.4.1
Description: This Nodal Protocol Revision Request (NPRR) synchronizes the Nodal Protocols with PRR682, EECP Event Realignment, which was approved by the ERCOT Board on November 14, 2006.
Reason: This revision implements the changes to EECP Steps to allow earlier communication of reliability concerns by ERCOT to Market Participants (MPs) and concerned entities.