MIS LOG IN

NPRR096

Summary

Title Revisions to the RMR Startup Energy Payment
Next Group
Next Step
Status Approved on 03/18/2008
Effective Dates
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (04/01/08 Nodal Protocols Library)

Action

Date Gov Body Action Taken Next Steps
03/18/2008 BOARD Approved
03/06/2008 TAC Recommended for Approval ERCOT Board consideration of NPRR096
02/21/2008 PRS Recommended for Approval TAC consideration of NPRR096
01/17/2008 PRS Recommended for Approval Review of the Impact Analysis and Recommendation Report for NPRR096.

Voting Record

Date Gov Body Motion Result
03/18/2008 BOARD Approve NPRR096 as recommended by TAC. Passed
03/06/2008 TAC To recommend approval as recommended by PRS. Passed
02/21/2008 PRS To forward the Impact Analysis and Recommendation Report to TAC. Passed
01/17/2008 PRS To recommend approval of this NPRR as submitted. Passed

Background

Status: Approved
Date Posted: Jan 7, 2008
Sponsor: ERCOT Staff
Urgent: No
Sections: 6.6.6.2, RMR Payment for Energy
Description: This Nodal Protocol Revision Request (NPRR) incorporates language from the COMS Eligibility Process for Settlements Requirements (B2) (v3.0) (Eligibility Process) document approved by the Transition Plan Task Force (TPTF) on October 8, 2007. The proposed language is consistent with the language in the Eligibility Process to determine if a Reliability Must Run (RMR) Unit is to be compensated for its startup costs as well as Protocol Sections 5.6.2, RUC Startup Cost Eligibility, and 5.6.3, Forced Outage of a RUC-Committed Resource.
Reason: The Nodal Protocols need provisions for the determination of eligibility for compensation for startup costs in the event of multiple starts in a day from the Day Ahead Market (DAM) and Reliability Unit Commitment (RUC) markets.

Key Documents

Related Content