MIS LOG IN

NPRR1079

Summary

Title Day-Ahead Market RRS / ECRS 48-Hour Report Clarification
Next Group
Next Step
Status Approved on 08/19/2021
Effective Dates
10/14/2022

Action

Date Gov Body Action Taken Next Steps
08/19/2021 PUCT Approved
08/10/2021 BOARD Recommended for Approval PUCT for consideration
07/28/2021 TAC Recommended for Approval Board for consideration
07/15/2021 PRS Recommended for Approval TAC for consideration
06/10/2021 PRS Recommended for Approval PRS for Impact Analysis consideration

Voting Record

Date Gov Body Motion Result
08/19/2021 PUCT To approve NPRR1079 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307 Passed
08/10/2021 BOARD To recommend approval of NPRR1079 as recommended by TAC in the 7/28/21 TAC Report Passed
07/28/2021 TAC To recommend approval of NPRR1079 as recommended by PRS in the 7/15/21 PRS Report Passed
07/15/2021 PRS To endorse and forward to TAC the 6/10/21 PRS Report and Impact Analysis for NPRR1079 Passed
06/10/2021 PRS To recommend approval of NPRR1079 as submitted Passed

Background

Status: Approved
Date Posted: May 20, 2021
Sponsor: ERCOT
Urgent: No
Sections: 3.2.5
Description: This Nodal Protocol Revision Request (NPRR) splits ERCOT Contingency Reserve Service (ECRS) and Fast Frequency Reserve (FFR) project language from the 48-hour Day-Ahead Market (DAM) report requirements.
Reason: Market efficiencies or enhancements

Key Documents

Related Content