NPRR1096

Summary

Title Require Sustained Two-Hour Capability for ECRS and Four-Hour Capability for Non-Spin
Next Group
Next Step
Status Approved on 05/12/2022
Effective Dates
12/09/2022

Sections 2.1, 3.17.3, and 8.1.1.2

06/09/2023

All remaining sections

Action

Date Gov Body Action Taken Next Steps
05/12/2022 PUCT Approved
04/28/2022 BOARD Recommended for Approval PUCT for consideration
03/30/2022 TAC Recommended for Approval Board for consideration
03/09/2022 PRS Recommended for Approval TAC for consideration
02/09/2022 PRS Recommended for Approval PRS for Impact Analysis consideration
10/14/2021 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
05/12/2022 PUCT To approve NPRR1096 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization
04/28/2022 BOARD To recommend approval of NPRR1096 as recommended by TAC in the 3/30/22 TAC Report Passed
03/30/2022 TAC To recommend approval of NPRR1096 as recommended by PRS in the 3/9/22 PRS Report Passed
03/09/2022 PRS To endorse and forward to TAC the 2/9/22 PRS Report and Revised Impact Analysis for NPRR1096 with a recommended priority of 2022 and rank of 2650 Passed
02/09/2022 PRS To recommend approval of NPRR1096 as amended by the 11/3/21 ERCOT comments Passed
10/14/2021 PRS To table NPRR1096 and refer the issue to ROS and WMS Passed

Background

Status: Approved
Date Posted: Sep 28, 2021
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 3.17.3, 3.17.4, 8.1.1.2, 8.1.1.3.3, and 8.1.1.3.4
Description: This Nodal Protocol Revision Request (NPRR) requires Resources that provide ERCOT Contingency Reserve Service (ECRS) to limit their responsibility to a quantity of capacity that is capable of being sustained for two consecutive hours and/or Non-Spinning Reserve (Non-Spin) to limit their responsibility to a quantity of capacity that is capable of being sustained for four consecutive hours. Additionally, this NPRR also requires ERCOT to conduct unannounced tests on Energy Storage Resources (ESRs) that are providing ECRS and/or Non-Spin in Real-Time.
Reason: Addresses current operational issues