NPRR1117

Summary

Title Related to SMOGRR025, Modifications to Line Loss Compensation Requirement for EPS Metering
Next Group
Next Step
Status Approved on 05/12/2022
Effective Dates
06/01/2022

Action

Date Gov Body Action Taken Next Steps
05/12/2022 PUCT Approved
04/28/2022 BOARD Recommended for Approval Revision Request Consideration
04/13/2022 TAC Recommended for Approval Revision Request Consideration
03/30/2022 TAC Deferred/Tabled Revision Request Consideration
03/09/2022 PRS Recommended for Approval Revision Request Consideration
02/09/2022 PRS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
05/12/2022 PUCT to approve NPRR1117 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization Passed
04/28/2022 BOARD to recommend approval of NPRR1117 as recommended by TAC in the 4/13/22 TAC Report Passed
04/13/2022 TAC to recommend approval of NPRR1117 as recommended by PRS in the 3/9/22 PRS Report Passed
03/30/2022 TAC to table NPRR1117 Passed
03/09/2022 PRS to endorse and forward to TAC the 2/9/22 PRS Report and Impact Analysis for NPRR1117 Passed
02/09/2022 PRS to recommend approval of NPRR1117 as submitted Passed

Background

Status: Approved
Date Posted: Jan 21, 2022
Sponsor: ERCOT
Urgent: No
Sections: 10.3.2.2 and 11.1.5
Description: This Nodal Protocol Revision Request (NPRR) aligns the Protocols with Settlement Meter Operating Guide (SMOG) revisions allowing for losses in short runs of connecting lines to be disregarded in instances where the ERCOT-Polled Settlement (EPS) Meter is not physically placed at the Point of Interconnection (POI).
Reason: Addresses current operational issues; Market efficiencies or enhancements