MIS LOG IN

NPRR1127

Summary

Title Clarification of ERCOT Hotline Uses
Next Group
Next Step
Status Approved on 11/03/2022
Effective Dates
12/01/2022

Action

Date Gov Body Action Taken Next Steps
11/03/2022 PUCT Approved
10/18/2022 BOARD Recommended for Approval Revision Request Consideration
09/28/2022 TAC Recommended for Approval Revision Request Consideration
06/27/2022 TAC Deferred/Tabled Revision Request Consideration
06/09/2022 PRS Recommended for Approval Revision Request Consideration
05/11/2022 PRS Recommended for Approval Impact Analysis Consideration
04/14/2022 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
11/03/2022 PUCT to approve NPRR1127 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization Passed
10/18/2022 BOARD to recommend approval of NPRR1127 as recommended by TAC in the 9/28/22 TAC Report Passed
09/28/2022 TAC to recommend approval of NPRR1127 as recommended by PRS in the 6/9/22 PRS Report Passed
06/27/2022 TAC to table NPRR1127 Passed
06/09/2022 PRS to endorse and forward to TAC the 5/11/22 PRS Report as amended by the 6/8/22 DC Energy comments and the 3/23/22 Impact Analysis for NPRR1127 Passed
05/11/2022 PRS to recommend approval of NPRR1127 as amended by the 4/12/22 DC Energy comments Passed
04/14/2022 PRS to table NPRR1127 and refer the issue to ROS Passed

Background

Status: Approved
Date Posted: Mar 23, 2022
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 6.5.9.3.1, 6.5.9.3.3, 6.5.9.4, 6.5.9.4.2, 16.2.1, 16.2.1.1, 16.19, 23G
Description: This Nodal Protocol Revision Request (NPRR) clarifies which Entities are required to have Hotline and 24-hour, seven-day-per-week communications with ERCOT and requires that those Entities answer each Hotline call in order to proactively ensure situational awareness in emergency situations.
Reason: Addresses current operational issues; Regulatory requirements

Key Documents