Title Enhance Exceptional Fuel Cost Process
Next Group
Next Step
Status Approved on 06/29/2023
Effective Dates
06/30/2023

Action

Date Gov Body Action Taken Next Steps
06/29/2023 PUCT Approved
06/20/2023 BOARD Recommended for Approval Revision Request Consideration
06/05/2023 TAC Recommended for Approval Revision Request Consideration
05/23/2023 TAC Deferred/Tabled Revision Request Consideration
05/10/2023 PRS Recommended for Approval Revision Request Consideration

Voting Record

Date Gov Body Motion Result
06/29/2023 PUCT to approve NPRR1177 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization Passed
06/20/2023 BOARD to recommend approval of NPRR1177 as recommended by TAC in the 6/5/23 TAC Report Passed
06/05/2023 TAC to recommend approval of NPRR1177 as recommended by PRS in the 5/10/23 PRS Report, as amended by the 6/1/23 Constellation comments, and the 5/16/23 Impact Analysis; with a recommended effective date of the day after Public Utility Commission of Texas (PUCT) approval and a recommended sunset date of January 1, 2025 Passed
05/23/2023 TAC to table NPRR1177 Passed
05/10/2023 PRS to grant NPRR1177 Urgent status; to recommend approval of NPR1177 as revised by PRS and to forward to TAC NPRR1177 Passed

Background

Status: Approved
Date Posted: Apr 27, 2023
Sponsor: Constellation
Urgent: Yes
Sections: 2.1 and 4.4.9.4.1
Description: This Nodal Protocol Revision Request (NPRR) enables Generation Resources to file Exceptional Fuel Costs that include contractual cost and pipeline-mandated costs, and enhances the process for ERCOT and the Independent Market Monitor (IMM) to verify these costs.
Reason: Addresses current operational issues; Meets Strategic goals; Market efficiencies or enhancements