NPRR1180

Summary

Title Inclusion of Forecasted Load in Planning Analyses
Next Group TAC
Next Step Revision Request Consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
10/30/2024 TAC Deferred/Tabled Revision Request Consideration
10/17/2024 PRS Recommended for Approval Revision Request Consideration
09/12/2024 PRS Recommended for Approval Impact Analysis Consideration
06/14/2023 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
10/30/2024 TAC to table NPRR1180 Passed
10/17/2024 PRS to endorse and forward to TAC the 9/12/24 PRS Report and 10/16/24 Impact Analysis for NPRR1180 Passed
09/12/2024 PRS to recommend approval of NPRR1180 as amended by the 8/28/24 ERCOT comments Passed
06/14/2023 PRS to table NPRR1180 and refer the issue to ROS Passed

Background

Status: Pending
Date Posted: May 11, 2023
Sponsor: Oncor
Urgent: No
Sections: 2.1, 3.11.4.1, 3.11.4.1.1, 3.11.4.6, 3.11.4.7, 3.11.4.9
Description: This Nodal Protocol Revision Request (NPRR) revises the Protocols to address recent amendments to P.U.C. SUBST. R. 25.101, Certification Criteria, which became effective on December 20, 2022. Specifically, NPRR1180 incorporates the requirement in P.U.C. SUBST. R. 25.101(b)(3)(A)(ii)(II) for any reliability-driven transmission project review conducted by ERCOT to incorporate the historical load, forecasted load growth, and additional load seeking interconnection, in the ERCOT independent review.
Reason: Regulatory requirements