NPRR1182
Summary
Title | Inclusion of Controllable Load Resources and Energy Storage Resources in the Constraint Competitiveness Test Process |
---|---|
Next Group | |
Next Step | |
Status | Approved on 10/12/2023 |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
10/12/2023 | PUCT | Approved | |
08/31/2023 | BOARD | Recommended for Approval | PUCT for consideration |
07/25/2023 | TAC | Recommended for Approval | Board for consideration |
07/13/2023 | PRS | Recommended for Approval | TAC for consideration |
06/14/2023 | PRS | Recommended for Approval | PRS for Impact Analysis consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
10/12/2023 | PUCT | To approve NPRR1182 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization | Passed |
08/31/2023 | BOARD | To recommend approval of NPRR1182 as recommended by TAC in the 7/25/23 TAC Report | Passed |
07/25/2023 | TAC | To recommend approval of NPRR1182 as recommended by PRS in the 7/13/23 PRS Report | Passed |
07/13/2023 | PRS | To endorse and forward to TAC the 6/14/23 PRS Report and 5/22/23 Impact Analysis for NPRR1182 with a recommended priority of 2024 and rank of 4030 | Passed |
06/14/2023 | PRS | To recommend approval of NPRR1182 as submitted | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | May 22, 2023 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 3.19.1, 3.19.2, 3.19.3, and 3.19.4 |
Description: | This Nodal Protocol Revision Request (NPRR) incorporates Controllable Load Resources and Energy Storage Resources (ESRs) into both the Long-Term and Security-Constrained Economic Dispatch (SCED) versions of the Constraint Competitiveness Test (CCT). In the case of Controllable Load Resources, the Resources will not themselves be mitigated but will be used to identify if a Market Participant has market power in resolving a constraint on the transmission system. As is the case for other Resources, registration data will be used for these Resources in the Long-Term CCT process and Real-Time telemetry will be used in the SCED CCT process. |
Reason: | Market efficiencies or enhancements |
Key Documents
May 22, 2023 - docx - 30.6 KB
Jun 15, 2023 - xls - 143 KB
Jun 15, 2023 - docx - 48.9 KB
Jul 14, 2023 - xls - 143.5 KB
Jul 14, 2023 - docx - 50.1 KB
Jul 27, 2023 - xls - 140.5 KB
Jul 27, 2023 - docx - 50.5 KB
Sep 1, 2023 - docx - 50.7 KB
Oct 13, 2023 - docx - 50.7 KB