NPRR1197

Summary

Title Optional Exclusion of Load from Netting at ERCOT-Polled Settlement (EPS) Metering Facilities which Include Resources
Next Group
Next Step
Status Approved on 06/13/2024
Effective Dates
07/01/2024

Action

Date Gov Body Action Taken Next Steps
06/13/2024 PUCT Approved
04/23/2024 BOARD Recommended for Approval PUCT for consideration
03/27/2024 TAC Recommended for Approval Board for consideration
03/20/2024 PRS Recommended for Approval TAC for consideration
02/08/2024 PRS Recommended for Approval PRS for Impact Analysis consideration
10/12/2023 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
06/13/2024 PUCT To approve NPRR1197 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization Passed
04/23/2024 BOARD To recommend approval of NPRR1197 as recommended by TAC in the 3/27/24 TAC Report Passed
03/27/2024 TAC To recommend approval of NPRR1197 as recommended by PRS in the 3/20/24 PRS Report Passed
03/20/2024 PRS To endorse and forward to TAC the 2/8/24 PRS Report and 2/28/24 Impact Analysis for NPRR1197 Passed
02/08/2024 PRS To recommend approval of NPRR1197 as amended by the 2/7/24 Oncor comments as revised by PRS Passed
10/12/2023 PRS To table NPRR1197 and refer the issue to WMS Passed

Background

Status: Approved
Date Posted: Aug 31, 2023
Sponsor: Engie
Urgent: No
Sections: 10.3.2.3 and 11.1.6
Description: This Nodal Protocol Revision Request (NPRR) adds the ability for Resources to separately meter and settle Load(s) located behind the EPS metering point at the Resource’s POI.
Reason: General system and/or process improvement(s)

Key Documents

Related Content