NPRR120

Summary

Title Corrections and Clarifications for Real Time Settlements
Next Group
Next Step
Status Approved on 07/15/2008
Effective Dates
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (08/01/08 Nodal Protocols Library)

Action

Date Gov Body Action Taken Next Steps
06/26/2008 TAC Recommended for Approval ERCOT Board consideration
06/19/2008 PRS Recommended for Approval Consideration of NPRR120 by TAC
07/15/2008 BOARD Approved
05/22/2008 PRS Recommended for Approval Review of Impact Analysis and Recommendation Report.
04/18/2008 PRS Referred Review by the TPTF.

Voting Record

Date Gov Body Motion Result
06/26/2008 TAC To recommend approval of NPRR120 as recommended by PRS. Passed
06/19/2008 PRS To endorse the Impact Analysis and Recommendation Report for NPRR120, and forward the documents to TAC. Passed
07/15/2008 BOARD To approve NPRR120 as recommended by TAC. Passed
05/22/2008 PRS To recommend approval of NPRR120 as submitted. Passed
04/18/2008 PRS To refer NPRR120 to TPTF for review. Passed

Background

Status: Approved
Date Posted: Mar 27, 2008
Sponsor: ERCOT Staff
Urgent: No
Sections: 6.6.3.1, Real Time Energy Imbalance Payment or Charge at a Resource Node; 6.6.5.1.1, Base Point Deviation Charge for Over Generation; 6.6.6.1, RMR Standby Payment; 6.6.8.1, Black Start Capacity Payment; 6.6.9.1, Payment for Emergency Power Increase Directed by ERCOT; and 6.6.10, Real Time Revenue Neutrality Allocation.
Description: This Nodal Protocol Revision Request (NPRR) makes corrections and clarifications to existing formulas for Real-Time Settlement.
Reason: To have the Protocols accurately reflect formulas related to Settlement.