Title | Revisions to QSE Operations and Termination Requirements, and Elimination of Providing Certain Market Participant Principal Information |
---|---|
Next Group | |
Next Step | |
Status | Approved on 04/11/2024 |
Effective Dates |
05/01/2024
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
04/11/2024 | PUCT | Approved | |
02/27/2024 | BOARD | Recommended for Approval | Revision Request Consideration |
01/24/2024 | TAC | Recommended for Approval | Revision Request Consideration |
01/11/2024 | PRS | Recommended for Approval | Revision Request Consideration |
12/15/2023 | PRS | Recommended for Approval | Impact Analysis Consideration |
11/09/2023 | PRS | Deferred/Tabled | Language Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
04/11/2024 | PUCT | to approve NPRR1206 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization | Passed |
02/27/2024 | BOARD | to recommend approval of NPRR1206 as recommended by TAC in the 1/24/24 TAC Report | Passed |
01/24/2024 | TAC | to recommend approval of NPRR1206 as recommended by PRS in the 1/11/24 PRS Report | Passed |
01/11/2024 | PRS | to endorse and forward to TAC the 12/15/23 PRS Report and 10/25/23 Impact Analysis for NPRR1206 | Passed |
12/15/2023 | PRS | to recommend approval of NPRR1206 as amended by the 12/14/23 ERCOT comments as revised by PRS | Passed |
11/09/2023 | PRS | to table NPRR1206 and refer the issue to WMS | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Oct 25, 2023 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 2.1, 16.2.1, 16.2.1.2, 16.2.3.2, 16.2.3.3, 16.3.4, 16.5.1.1, 16.5.3, 16.5.4, 16.8.3.1, 23 Form A, 23 Form B, 23 Form E, 23 Form G, 23 Form I, 23 Form J, 23 Form M |
Description: | This Nodal Protocol Revision Request (NPRR) clarifies the types of Qualified Scheduling Entities (QSEs) required to have a Hotline and a 24-hour, seven-day-per-week (24x7) control or operations center. This NPRR also reconciles: (1) the deadline by which QSEs representing Resource Entities that own or control Resources must provide notice that they are terminating their representation; and (2) the deadline for Resource Entities that own or control Resources to change QSEs by proposing a 45-day timeline by which a QSE representing a Resource must give notice of the effective Termination Date, and clarifies that the Resource Entity’s change in QSE designation takes 45 days to become effective in the Network Operations Model. In addition, this NPRR also eliminates the requirement to provide certain unnecessary Market Participant Principal information. Finally, this NPRR proposes the deletion of duplicative language concerning the authority of a registered Data Agent-Only QSE, and further phases out acceptance of paper checks and the use of communication via fax. |
Reason: | Strategic Plan Objective 1 |
Key Documents
Oct 25, 2023 - docx - 18.9 KB
Nov 14, 2023 - xls - 143.5 KB
Nov 14, 2023 - docx - 241.9 KB
Dec 7, 2023 - xls - 142 KB
Dec 14, 2023 - docx - 225.5 KB
Dec 14, 2023 - docx - 230.1 KB
Dec 19, 2023 - xls - 143 KB
Dec 19, 2023 - docx - 242.3 KB
Jan 16, 2024 - xls - 138 KB
Jan 16, 2024 - docx - 243.1 KB
Jan 29, 2024 - xls - 140.5 KB
Jan 29, 2024 - docx - 252.1 KB
Feb 28, 2024 - docx - 252.4 KB
Apr 15, 2024 - docx - 252.5 KB