Title Remove Verbal Dispatch Instruction (VDI) Requirement for Deployment and Recall of Load Resources and Emergency Response Service (ERS) Resources
Next Group
Next Step
Status Approved on 09/26/2024
Effective Dates
10/01/2024

Action

Date Gov Body Action Taken Next Steps
09/26/2024 PUCT Approved
08/20/2024 BOARD Recommended for Approval Revision Request Consideration
07/31/2024 TAC Recommended for Approval Revision Request Consideration
07/18/2024 PRS Recommended for Approval Revision Request Consideration
06/13/2024 PRS Recommended for Approval Impact Analysis Consideration
03/20/2024 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
09/26/2024 PUCT to approve NPRR1217 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization Passed
08/20/2024 BOARD to recommend approval of NPRR1217 as recommended by TAC in the 7/31/24 TAC Report Passed
07/31/2024 TAC to recommend approval of NPRR1217 as recommended by PRS in the 7/18/24 PRS Report Passed
07/18/2024 PRS to endorse and forward to TAC the 6/13/24 PRS Report and 5/14/24 Revised Impact Analysis for NPRR1217 with a recommended priority of 2024 and rank of 4100 Passed
06/13/2024 PRS to recommend approval of NPRR1217 as submitted Passed
03/20/2024 PRS To table NPRR1217 and refer the issue to ROS Passed

Background

Status: Approved
Date Posted: Feb 28, 2024
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 3.14.3.1, 6.5.9.4.1, 6.5.9.4.2, and 8.1.3.3.3
Description: This Nodal Protocol Revision Request (NPRR) removes the requirement for Load Resources and Emergency Response Service (ERS) Resources to be deployed using a Verbal Dispatch Instruction (VDI) from ERCOT and updates a reference in paragraph (3)(a) of Section 6.5.9.4.1 to be consistent with changes made in NPRR1176, Update to EEA Trigger Levels.
Reason: General system and/or process improvement(s)

Key Documents

Related Content