Summary

Title Exclusion of Lubbock Load from Securitization Charges
Next Group
Next Step
Status Approved on 09/26/2024
Effective Dates
10/01/2024

Action

Date Gov Body Action Taken Next Steps
09/26/2024 PUCT Approved
08/20/2024 BOARD Recommended for Approval PUCT for consideration
06/24/2024 TAC Recommended for Approval Board for consideration
06/13/2024 PRS Recommended for Approval TAC for consideration
05/09/2024 PRS Recommended for Approval PRS for Impact Analysis consideration

Voting Record

Date Gov Body Motion Result
09/26/2024 PUCT To approve NPRR1225 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization Passed
08/20/2024 BOARD To recommend approval of NPRR1225 as recommended by TAC in the 6/24/24 TAC Report Passed
06/24/2024 TAC To recommend approval of NPRR1225 as recommended by PRS in the 6/13/24 PRS Report Passed
06/13/2024 PRS To endorse and forward to TAC the 5/9/24 PRS Report and 4/11/24 Impact Analysis for NPRR1225 Passed
05/09/2024 PRS To recommend approval of NPRR1225 as submitted Passed

Background

Status: Approved
Date Posted: Apr 11, 2024
Sponsor: ERCOT
Urgent: No
Sections: 26.2, 27.3, and 27.5.4
Description: This Nodal Protocol Revision Request (NPRR) updates the Protocols to align with the Public Utility Commission of Texas’s (PUCT’s) decisions in PUCT Docket No. 56119, Petition of Electric Reliability Council of Texas, Inc. for Expedited Declaratory Order Regarding Public Utility Regulatory Act Chapter 39, Subchapter N; and Docket No. 56122, Petition of Electric Reliability Council of Texas, Inc. for Expedited Declaratory Order Regarding Public Utility Regulatory Act Chapter 39, Subchapter M. To comply with the PUCT’s declaratory orders, ERCOT changed its Settlement systems to implement the PUCT-ordered exclusions to be effective on or before March 4, 2024, the day on which the transfer of Lubbock Power and Light (LP&L) retail Customers to Retail Electric Providers (REPs) began. This NPRR reflects in the Protocols those exclusions.
Reason: Regulatory requirements