Summary

Title Estimated Demand Response Data
Next Group PRS
Next Step PRS for Impact Analysis consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
02/12/2025 PRS Recommended for Approval PRS for Impact Analysis consideration
05/09/2024 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
02/12/2025 PRS To recommend approval of NPRR1226 as amended by the 2/11/25 ERCOT comments Passed
05/09/2024 PRS To table NPRR1226 and refer the issue to WMS Passed

Background

Status: Pending
Date Posted: Apr 23, 2024
Sponsor: ERCOT Steel Mills
Urgent: No
Sections: 2.1, 2.2, 6.3.2, and 6.5.7.1.13
Description: This Nodal Protocol Revision Request (NPRR) directs ERCOT to prepare and publish estimated Demand response data showing aggregated State Estimated Load (SEL) load points selected by ERCOT. The selection of Loads to be aggregated for the report will be based on periodically updated off-line analysis of the frequency and magnitude of reductions observed in historical State Estimator load data that is associated with market signals such as Locational Marginal Prices (LMPs), high levels of summer month ERCOT load, ERCOT-wide appeal(s) through public voluntary energy appeal, or other ERCOT actions.
Reason: Strategic Plan Objective 2