NPRR1229

Summary

Title Real-Time Constraint Management Plan Cost Recovery Payment
Next Group TAC
Next Step TAC for consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
04/09/2025 PRS Recommended for Approval TAC for consideration
03/12/2025 PRS Recommended for Approval PRS for Impact Analysis consideration
06/13/2024 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
04/09/2025 PRS To endorse and forward to TAC the 3/12/25 PRS Report as amended by the 3/20/25 ERCOT comments and the 4/8/25 Impact Analysis for NPRR1229 with a recommended effective date of upon system implementation for Section 9.5.3 with a recommended priority of 2028 and rank of 5100 and the first of the month following PUCT approval for the remaining sections Passed
03/12/2025 PRS To recommend approval of NPRR1229 as amended by the 3/6/25 WMS comments as revised by PRS Passed
06/13/2024 PRS To table NPRR1229 and refer the issue to ROS and WMS Passed

Background

Status: Pending
Date Posted: May 6, 2024
Sponsor: STEC
Urgent: No
Sections: 4.4.9.3.3, 6.6.3.9 (new), 6.6.3.10 (new), 6.6.3.11 (new), and 9.5.3
Description: This Nodal Protocol Revision Request (NPRR) creates a process that compensates a Qualified Scheduling Entity (QSE) when a Constraint Management Plan (CMP) or ERCOT-directed switching instruction implemented by ERCOT causes the trip of a Generation Resource when it would not have occurred absent those conditions.
Reason: General system and/or process improvement(s)