NPRR1234
Summary
Title | Interconnection Requirements for Large Loads and Modeling Standards for Loads 25 MW or Greater |
---|---|
Next Group | PRS |
Next Step | PRS for Impact Analysis consideration |
Status | Pending |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
02/12/2025 | PRS | Recommended for Approval | PRS for Impact Analysis consideration |
06/13/2024 | PRS | Deferred/Tabled | PRS for consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
02/12/2025 | PRS | To recommend approval of NPRR1234 as amended by the 1/24/25 ERCOT comments | Passed |
06/13/2024 | PRS | To table NPRR1234 and refer the issue to ROS | Passed |
Background
Status: | Pending |
---|---|
Date Posted: | May 28, 2024 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 2.1, 2.2, 3.1.1, 3.1.5.11, 3.3.2, 3.10.7.2, 3.10.7.5, 3.10.7.5.1, 3.15, 3.15.3, 3.22, 3.22.1, 3.22.1.1, 3.22.1.2, 3.22.1.3, 3.22.1.4 (new), 3.22.1.4, 3.22.2, 3.22.3, 16.5, and ERCOT Fee Schedule |
Description: | This Nodal Protocol Revision Request (NPRR) and the related PGRR establish interconnection and modeling requirements for “Large Loads”—defined in this NPRR to refer to one or more Facilities at a single site with an aggregate peak power Demand of 75 MW or more. ERCOT proposes these requirements based upon its experience with the interim large Load interconnection process implemented on March 25, 2022, analysis of operational events, and the discussion of various issues concerning Large Loads explored by the Large Flexible Load Task Force (LFLTF). Additionally, this NPRR facilitates the addition of a new study process for Large Loads seeking to interconnect to the ERCOT system. This process is described in the accompanying PGRR. This NPRR also adds a requirement that any Resource Entity that adds 20 MW or more of Load at any site with an existing Generation Resource shall submit a new Reactive Power study. The study must demonstrate the continued compliance of the Generation Resource with Voltage Support Service (VSS) requirements. This NPRR also establishes specific Subsynchronous Oscillation (SSO) requirements for Large Loads and revises and supplements SSO-related definitions, in addition to clarifying existing SSO requirements. Furthermore, although the primary focus of this NPRR is Loads that are 75 MW or larger, this NPRR also establishes new standards for the identification and classification of a site with an aggregate peak Demand of 25 MW or more at a common substation in ERCOT Network Operations Model. Such information will provide ERCOT visibility of the locations of these Loads for operational and planning purposes. Finally, this NPRR adds a fee for Large Load Interconnection Study Requests to the ERCOT Fee Schedule. |
Reason: | Strategic Plan Objective 1 |
Key Documents
May 28, 2024 - docx - 99.7 KB
May 28, 2024 - docx - 31.6 KB
Jun 18, 2024 - xls - 140 KB
Jun 18, 2024 - docx - 99.7 KB
Jun 26, 2024 - docx - 72.6 KB
Aug 15, 2024 - xls - 137.5 KB
Jul 11, 2024 - docx - 22.2 KB
Aug 12, 2024 - docx - 30.5 KB
Aug 15, 2024 - docx - 90.2 KB
Sep 18, 2024 - docx - 76.4 KB
Nov 11, 2024 - docx - 77 KB
Dec 12, 2024 - docx - 78.7 KB
Dec 16, 2024 - docx - 93.2 KB
Jan 24, 2025 - docx - 92.4 KB
Feb 6, 2025 - xls - 137.5 KB
Feb 6, 2025 - docx - 22.3 KB
Feb 11, 2025 - docx - 91.6 KB
Feb 14, 2025 - xls - 141 KB
Feb 14, 2025 - docx - 112.7 KB