- Home
- Market Rules
- Issues
NPRR1246
Summary
Title | Energy Storage Resource Terminology Alignment for the Single-Model Era |
---|---|
Next Group | TAC |
Next Step | TAC for consideration |
Status | Pending |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
12/03/2024 | BOARD | Remanded | TAC for consideration |
11/20/2024 | TAC | Recommended for Approval | Board for consideration |
11/14/2024 | PRS | Recommended for Approval | TAC for consideration |
10/17/2024 | PRS | Recommended for Approval | PRS for Impact Analysis consideration |
09/12/2024 | PRS | Deferred/Tabled | PRS for consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
12/03/2024 | BOARD | To remand NPRR1246 to TAC | Passed |
11/20/2024 | TAC | To recommend approval of NPRR1246 as recommended by PRS in the 11/14/24 PRS Report | Passed |
11/14/2024 | PRS | To endorse and forward to TAC the 10/17/24 PRS Report and 7/31/24 Impact Analysis for NPRR1246 | Passed |
10/17/2024 | PRS | To recommend approval of NPRR1246 as amended by the 9/20/24 ERCOT comments | Passed |
09/12/2024 | PRS | To table NPRR1246 | Passed |
Background
Status: | Pending |
---|---|
Date Posted: | Jul 31, 2024 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 1.3.1.1, 1.3.1.2, 1.6.5, 2.1, 2.2, 3.1.1, 3.1.3.2, 3.1.4.5, 3.1.5.1, 3.1.5.11, 3.6.1, 3.8.5, 3.10.1, 3.10.3, 3.10.6, 3.10.7.1.4, 3.10.7.2, 3.10.7.6, 3.10.7.7, 3.14.1.9, 3.14.4.1, 3.14.4.5, 3.14.4.7, 3.17.1, 3.17.2, 3.17.3, 3.17.4, 3.18, 3.22.1.2, 3.22.1.3, 3.22.1.4, 3.22.2, 3.22.3, 4.4.6.3, 4.4.7.1, 4.4.7.3, 4.4.9.3.3, 6.5.1.1, 6.5.3, 6.5.5.1, 6.5.7.1.13, 6.5.7.4, 6.5.7.4.1, 6.5.7.6.2.2, 6.5.7.6.2.3, 6.5.7.6.2.4, 6.5.7.8, 6.5.8, 6.5.9.4, 6.5.9.4.2, 6.6.3.6, 6.6.5.2, 6.6.5.2.1, 6.6.5.4, 6.6.7.1, 6.6.9, 8.1, 8.1.1.1, 8.1.1.2.1.7, 8.1.1.4.1, 8.2, 8.4, 9.17.1, 9.19.1, 10.2.2, 10.3.2.1.6, 10.3.2.3, 10.3.2.4, 11.5.2, 11.5.2.1, 13.2.4, 16.5, 16.14, 26.2, 22E, 22H, 22L, 22N, 22P, and 23I |
Description: | This Nodal Protocol Revision Request (NPRR) inserts terminology associated with Energy Storage Resources (ESRs) in the appropriate places throughout the Protocols, aligning provisions and requirements for ESRs with those already in place for Generation Resources and Controllable Load Resources. This NPRR applies to ESRs in the future single-model era and should be implemented simultaneously with NPRR1014, BESTF-4 Energy Storage Resource Single Model. |
Reason: | General system and/or process improvement(s) |