NPRR1246

Summary

Title Energy Storage Resource Terminology Alignment for the Single-Model Era
Next Group TAC
Next Step TAC for consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
12/03/2024 BOARD Remanded TAC for consideration
11/20/2024 TAC Recommended for Approval Board for consideration
11/14/2024 PRS Recommended for Approval TAC for consideration
10/17/2024 PRS Recommended for Approval PRS for Impact Analysis consideration
09/12/2024 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
12/03/2024 BOARD To remand NPRR1246 to TAC Passed
11/20/2024 TAC To recommend approval of NPRR1246 as recommended by PRS in the 11/14/24 PRS Report Passed
11/14/2024 PRS To endorse and forward to TAC the 10/17/24 PRS Report and 7/31/24 Impact Analysis for NPRR1246 Passed
10/17/2024 PRS To recommend approval of NPRR1246 as amended by the 9/20/24 ERCOT comments Passed
09/12/2024 PRS To table NPRR1246 Passed

Background

Status: Pending
Date Posted: Jul 31, 2024
Sponsor: ERCOT
Urgent: No
Sections: 1.3.1.1, 1.3.1.2, 1.6.5, 2.1, 2.2, 3.1.1, 3.1.3.2, 3.1.4.5, 3.1.5.1, 3.1.5.11, 3.6.1, 3.8.5, 3.10.1, 3.10.3, 3.10.6, 3.10.7.1.4, 3.10.7.2, 3.10.7.6, 3.10.7.7, 3.14.1.9, 3.14.4.1, 3.14.4.5, 3.14.4.7, 3.17.1, 3.17.2, 3.17.3, 3.17.4, 3.18, 3.22.1.2, 3.22.1.3, 3.22.1.4, 3.22.2, 3.22.3, 4.4.6.3, 4.4.7.1, 4.4.7.3, 4.4.9.3.3, 6.5.1.1, 6.5.3, 6.5.5.1, 6.5.7.1.13, 6.5.7.4, 6.5.7.4.1, 6.5.7.6.2.2, 6.5.7.6.2.3, 6.5.7.6.2.4, 6.5.7.8, 6.5.8, 6.5.9.4, 6.5.9.4.2, 6.6.3.6, 6.6.5.2, 6.6.5.2.1, 6.6.5.4, 6.6.7.1, 6.6.9, 8.1, 8.1.1.1, 8.1.1.2.1.7, 8.1.1.4.1, 8.2, 8.4, 9.17.1, 9.19.1, 10.2.2, 10.3.2.1.6, 10.3.2.3, 10.3.2.4, 11.5.2, 11.5.2.1, 13.2.4, 16.5, 16.14, 26.2, 22E, 22H, 22L, 22N, 22P, and 23I
Description: This Nodal Protocol Revision Request (NPRR) inserts terminology associated with Energy Storage Resources (ESRs) in the appropriate places throughout the Protocols, aligning provisions and requirements for ESRs with those already in place for Generation Resources and Controllable Load Resources. This NPRR applies to ESRs in the future single-model era and should be implemented simultaneously with NPRR1014, BESTF-4 Energy Storage Resource Single Model.
Reason: General system and/or process improvement(s)