NPRR1248

Summary

Title Correction to NPRR1197, Optional Exclusion of Load from Netting at EPS Metering Facilities which Include Resources
Next Group
Next Step
Status Approved on 01/16/2025
Effective Dates
02/01/2025

Action

Date Gov Body Action Taken Next Steps
01/16/2025 PUCT Approved
12/03/2024 BOARD Recommended for Approval PUCT for consideration
10/30/2024 TAC Recommended for Approval Board for consideration
10/17/2024 PRS Recommended for Approval TAC for consideration
09/12/2024 PRS Recommended for Approval PRS for Impact Analysis consideration

Voting Record

Date Gov Body Motion Result
01/16/2025 PUCT To approve NPRR1248 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization Passed
12/03/2024 BOARD To recommend approval of NPRR1248 as recommended by TAC in the 10/30/24 TAC Report Passed
10/30/2024 TAC To recommend approval of NPRR1248 as recommended by PRS in the 10/17/24 PRS Report Passed
10/17/2024 PRS To endorse and forward to TAC the 9/12/24 PRS Report and 8/16/24 Impact Analysis for NPRR1248 Passed
09/12/2024 PRS To recommend approval of NPRR1248 as submitted Passed

Background

Status: Approved
Date Posted: Aug 16, 2024
Sponsor: ERCOT
Urgent: No
Sections: 11.1.6
Description: This Nodal Protocol Revision Request (NPRR) corrects language in Section 11.1.6 which was implemented with the July 1, 2024 Protocols following Public Utility Commission of Texas (PUCT) approval of NPRR1197, Optional Exclusion of Load from Netting at ERCOT-Polled Settlement (EPS) Metering Facilities which Include Resources. The NPRR1197 2/8/24 PRS Report did not correctly reflect the PRS vote “to recommend approval of NPRR1197 as amended by the 2/7/24 Oncor comments as revised by PRS” in paragraph (6) of Section 11.1.6. This error carried through the ensuing 3/27/24 TAC Report and 4/23/24 Board Report, and was approved by the PUCT on 6/13/24. This NPRR aligns the language within Section 11.1.6 with the intended PRS action from February 8, 2024.
Reason: General system and/or process improvement(s)