Summary

Title Incorporate ESR Charging Load Information into ICCP
Next Group PUCT
Next Step Revision Request Consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
02/04/2025 BOARD Recommended for Approval Revision Request Consideration
01/22/2025 TAC Recommended for Approval Revision Request Consideration
01/15/2025 PRS Recommended for Approval Revision Request Consideration
12/12/2024 PRS Deferred/Tabled Impact Analysis Consideration
11/14/2024 PRS Recommended for Approval Impact Analysis Consideration
10/17/2024 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
02/04/2025 BOARD to recommend approval of NPRR1253 as recommended by TAC in the 1/22/25 TAC Report and the 1/24/25 Revised Impact Analysis Passed
01/22/2025 TAC to recommend approval of NPRR1253 as recommended by PRS in the 1/15/25 ROS Report Passed
01/15/2025 PRS to endorse and forward to TAC the 12/12/24 PRS Report and 1/14/25 Impact Analysis for NPRR1253 with a recommended priority of 2025 and rank of 4225 Passed
12/12/2024 PRS to table NPRR1253 Passed
11/14/2024 PRS to recommend approval of NPRR1253 as amended by the 10/10/24 ERCOT comments Passed
10/17/2024 PRS to table NPRR1253 Passed

Background

Status: Pending
Date Posted: Oct 1, 2024
Sponsor: Ammper Power
Urgent: No
Sections: 6.3.2
Description: This Nodal Protocol Revision Request (NPRR) 1253 includes Wholesale Storage Load (WSL) charging load to the dataset ERCOT provides via Inter-Control Center Communications Protocol (ICCP).
Reason: Strategic Plan Objective 2