- Home
- Market Rules
- Issues
NPRR128
Summary
Title | Combined Cycle Power Blocks with Multiple Voltage Interconnections |
---|---|
Next Group | |
Next Step | |
Status | Approved on 11/17/2008 |
Effective Dates |
12/01/2010
or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (12/01/08 Nodal Protocols Library) |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
07/17/2008 | PRS | Deferred/Tabled | PRS Impact Analysis Review |
09/24/2008 | PRS | Recommended for Approval | Impact Analysis Review |
11/17/2008 | BOARD | Approved | |
11/06/2008 | TAC | Recommended for Approval | Board Consideration |
10/23/2008 | PRS | Recommended for Approval | TAC consideration |
06/19/2008 | PRS | Recommended for Approval | Impact Analysis Review |
05/22/2008 | PRS | Referred | Review by TPTF |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
07/17/2008 | PRS | To table NPRR128 pending development of an Impact Analysis. | Passed |
09/24/2008 | PRS | To recommend approval of the PRS Recommendation Report as amended by ERCOT’s comments. All Market Segments were present for the vote | Passed |
11/17/2008 | BOARD | Approved NPRR128 as recommended by TAC. | Passed |
11/06/2008 | TAC | To recommend approval as recommended as approved PRS. | Passed |
10/23/2008 | PRS | To endorse and forward the PRS Recommendation Report and Impact Analysis to TAC. | Passed |
06/19/2008 | PRS | To recommend approval of NPRR128 as submitted. | Passed |
05/22/2008 | PRS | To refer NPRR128 to the TPTF for consideration. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Apr 25, 2008 |
Sponsor: | Calpine |
Urgent: | No |
Sections: | 6.5.5.2 |
Description: | This Nodal Protocol Revision Request (NPRR) eliminates the unnecessary restriction that requires all generators in a combined cycle power block to be connected to the bulk electric system at the same voltage level. This change must be made for similarly situated combined cycle units to effectively participate in the very important nodal 168-hour test. Re-done resource asset registration forms (RARFs) must also be constructed and validated prior to implementing these changes. |
Reason: | Current nodal Protocol language defines each configuration of a combined cycle power block to be a single Resource so long as all of the power block’s individual generators are connected to the transmission system at the same nominal voltage level. This requirement is not necessary to the functionality of the ERCOT nodal systems and has unintended consequences on the market and on owners of facilities where generators in the same physically coupled power block have generators connected at different voltages. These facilities must have the generators registered on separate RARFs, which ultimately leads to numerous infeasibilities in Real- Time dispatch and results in capacity being stranded out of the market. (Example: a 2x1 power block, with one combustion turbine (CT) and the steam turbine (ST) connected at 138 Kv, and the remaining CT connected at an adjacent 345 Kv bus must be registered in the market with two RARFs. The ST can only be rated at maximum loading with both CTs on-line but the RARF for that 1x1 configuration can only show half of the ST’s capability since the other CT is registered separately.) The feasibility of Real-Time dispatch is impacted negatively in the sense that the units must move in the same directions up and down a common energy offer curve in response to Security-Constrained Economic Dispatch (SCED) assigned base points because they are physically interdependent. (Example: The 1x1 will have its own configuration in the RARF and flagged in the Current Operating Plan (COP) with its own energy offer curve and the 1x0 CT on 345 Kv will also have its own energy offer curve. SCED base points could conceivably be issued that would have each of the configurations moving in opposite directions on their respective energy offer curves, which would be infeasible due to the physical coupling of all the machines.) It’s also worthy of noting that a combined cycle power block with all generators connected at the same bus can very well end up on different buses at different voltages and resulting Locational Marginal Prices (LMPs) if that common bus has a bus tie breaker that has to be opened at any given time.The machines impacted by the current nodal Protocol language were interconnected to the ERCOT System in good faith and in compliance with the then rules of ERCOT’s Standard Generator Interconnect Agreement (SGIA). Stakeholders have gone to great lengths to ensure that the new market design does not disenfranchise or devalue existing assets or agreements so there is significant precedent for correcting this inequity, particularly when it has no value to the functionality of the ERCOT Market Management System (MMS) and other central systems. |
Key Documents
Apr 25, 2008 - doc - 95.5 KB
May 23, 2008 - doc - 94.5 KB
Jun 6, 2008 - doc - 41 KB
May 23, 2008 - xls - 116.5 KB
Jun 19, 2008 - doc - 94.5 KB
Jul 16, 2008 - doc - 41.5 KB
Jul 22, 2008 - doc - 97 KB
Sep 22, 2008 - doc - 41.5 KB
Sep 23, 2008 - doc - 113 KB
Sep 29, 2008 - doc - 99.5 KB
Oct 13, 2008 - doc - 48 KB
Oct 27, 2008 - doc - 102.5 KB
Nov 6, 2008 - doc - 105 KB
Nov 18, 2008 - doc - 100.5 KB