NPRR175
Summary
Title | Hub Bus List Clarification |
---|---|
Next Group | |
Next Step | |
Status | Approved on 08/18/2009 |
Effective Dates |
12/01/2010
or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (09/01/09 Nodal Protocols Library) |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
05/21/2009 | PRS | Recommended for Approval | PRS for Impact Analysis review. |
07/09/2009 | TAC | Recommended for Approval | TAC for consideration. |
08/18/2009 | BOARD | Approved | |
06/18/2009 | PRS | Recommended for Approval | TAC for consideration. |
08/06/2009 | TAC | Recommended for Approval | Board of Directors for consideration. |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
05/21/2009 | PRS | To recommend approval of NPRR175 as submitted. | Passed |
07/09/2009 | TAC | To table NPRR175. | Passed |
08/18/2009 | BOARD | To approve NPRR175 as recommended by TAC in the 8/6/09 TAC Recommendation Report. | Passed |
06/18/2009 | PRS | To endorse and forward the PRS Recommendation Report and Impact Analysis for NPRR175 to TAC. | Passed |
08/06/2009 | TAC | To recommend approval of NPRR175 as amended by ERCOT comments. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Apr 30, 2009 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 3.5.2.1, 3.5.2.2 |
Description: | This Nodal Protocol Revision Request (NPRR) updates the Hub lists to reflect the current network model by removing Hub Bus SHRTP which was a construct of planning and does not exist; and also by renaming Hub Bus FPPYD, which was actually two substations that were amalgamated for planning reasons, to FPPYD1 and FPPYD2. SDSES no longer has a 345 kV infrastructure. ALNSW1/2, CNTRY1/3, FRNYPP1/2, JEWETN/S MDANP1/2, RCHBR1/2, TRSES1/2, VENSWN/S denote planning constructs which should be generalized to the substation’s 345kV system. |
Reason: | This NPRR updates the Hub lists to reflect the current network model by removing Hub Bus SHRTP which was a construct of planning and does not exist; and also by renaming Hub Bus FPPYD, which was actually two substations that were amalgamated for planning reasons, to FPPYD1 and FPPYD2. |
Key Documents
Apr 30, 2009 - doc - 333 KB
Apr 30, 2009 - doc - 41.5 KB
May 22, 2009 - doc - 255 KB
Jun 16, 2009 - doc - 45 KB
Jun 22, 2009 - doc - 329 KB
Jul 9, 2009 - doc - 332 KB
Aug 6, 2009 - doc - 292.5 KB
Aug 7, 2009 - doc - 324.5 KB
Aug 19, 2009 - doc - 327 KB