Summary

Title Registration and Settlement of Distributed Generation (DG) Less Than One MW
Next Group
Next Step
Status Approved on 07/20/2010
Effective Dates
12/01/2010

All sections except for Sections 11.4.4.2 and 11.4.4.3

Action

Date Gov Body Action Taken Next Steps
06/03/2010 TAC Referred COPS consideration
05/18/2010 BOARD Remanded TAC consideration
04/08/2010 TAC Deferred/Tabled TAC consideration
07/20/2010 BOARD Approved
03/25/2010 PRS Recommended for Approval TAC consideration
02/18/2010 PRS Recommended for Approval PRS consider the Recommendation Report and Impact Analysis
05/06/2010 TAC Recommended for Approval BOD consideration
06/08/2010 COPS Recommended for Approval TAC consideration
07/01/2010 TAC Recommended for Approval ERCOT Board consideration

Voting Record

Date Gov Body Motion Result
06/03/2010 TAC To refer NPRR208 to COPS. Passed
05/18/2010 BOARD Remanded NPRR208 to TAC Passed
04/08/2010 TAC To table NPRR208 for one month Passed
07/20/2010 BOARD To approve NPRR208 as recommended by TAC in the 7/1/10 TAC Report and to assign a priority of Critical to the grey-boxed language. Passed
03/25/2010 PRS To endorse and forward the 2/18/10 PRS Report as amended by the 3/3/10 ERCOT comments and as revised by PRS and Impact Analysis for NPRR208 to TAC Passed
02/18/2010 PRS To recommend approval of NPRR208 as amended by the 1/29/10 PWG comments. Passed
05/06/2010 TAC To recommend approval of NPRR208 as recommended by PRS in the 03/25/10 PRS Report as revised by TAC. Passed
06/08/2010 COPS To recommend approval of NPRR208 as amended by COPS. Passed
07/01/2010 TAC To recommend approval of NPRR208 as amended by the 06/24/10 ERCOT comments and to assign a priority of High/Medium to the grey-boxed language. Passed

Background

Status: Approved
Date Posted: Jan 25, 2010
Sponsor: Don Tucker on behalf of the NOIE DRG Taskforce
Urgent: No
Sections: 2.1, Definitions 2.2, Acronyms 10.2.2, TSP and DSP Metered Entities 11.4.4.2, Load Reduction for Excess PhotoVoltaic Distributed Renewable Generation 11.4.4.3, Load Reduction for Excess Non-PhotoVoltaic Distributed Generation 16.5, Registration of Generation Resources, Loads Acting as a Resource and Emergency Interruptible Load Service Resources 18.2, Methodology 18.2.2, Load Profiles for Non-Interval Metered Loads 18.2.3, Load Profiles for Non-Metered Loads
Description: The Nodal Protocol Revision Request (NPRR) includes proposed language changes by the NOIE DRG Taskforce in regards to the registration requirements for Distributed Generation (DG) greater than 50 kW and less than or equal to one MW. In addition this NPRR synchronizes language approved through PRR756, Distributed Renewable Generation Modifications, with some recommended revisions consistent with the NOIE DRG Task force discussions. PRR756 was approved by ERCOT Board on 5/20/08 and was un-grey boxed upon system implementation on 11/21/09.
Reason: The reason for this revision is to incorporate changes approved in PRR756, clarified registration requirements for DG to allow all DG to be settled as negative Load and raise the threshold for DG that can be settled as negative Load. PRR756 language established the threshold for Distributed Renewable Generation (DRG) negative Load Settlement at less than fifty (50) kW. This NPRR establishes a DG registration threshold.