Resolution of Alignment Item A83 partially, A86, A87 partially, A88 partially, and A142 - Clarify Default Actions for Missing Data and Range of Valid Data Entries for Energy Offers
Next Group
Next Step
Status
Approved on 08/17/2010
Effective Dates
12/01/2010
or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (09/01/10 Nodal Protocols Library)
This Nodal Protocol Revision Request (NPRR) clarifies system actions if the Qualified Scheduling Entity (QSE) cancels a Resource Parameter submission, if a Current Operating Plan (COP) is not submitted for any hour, and/or if a conflict in Resource Status is encountered. The NPRR also clarifies that in each hour only one Combined Cycle Generation Resource in a Combined Cycle Train may be assigned one of the On-Line Resource Status codes.
Reason:
This change conforms the Nodal Protocols to the as-built Nodal system.