Summary
Title | Proxy Energy Offer Curve |
---|---|
Next Group | |
Next Step | |
Status | Approved on 09/21/2010 |
Effective Dates |
12/01/2010
All sections except for Section 6.5.7.3(5) 02/04/2014
Section 6.5.7.3(5) |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
09/21/2010 | BOARD | Approved | |
09/02/2010 | TAC | Recommended for Approval | ERCOT Board consideration of NPRR240 |
08/19/2010 | PRS | Recommended for Approval | TAC consideration of NPRR240 |
06/17/2010 | PRS | Deferred/Tabled | PRS language consideration |
07/22/2010 | PRS | Recommended for Approval | PRS Impact Analysis review |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
09/21/2010 | BOARD | To approve NPRR240 as recommended by TAC in the 9/2/10 TAC Report. | Passed |
09/02/2010 | TAC | To recommend approval of NPRR240 as recommended by PRS in the 8/19/10 PRS Report with a priority of High/Medium for the grey-boxed language. | Passed |
08/19/2010 | PRS | To endorse and forward the 7/22/10 PRS Report and Impact Analysis for NPRR240 to TAC and to recommend a priority of High/Medium. | Passed |
06/17/2010 | PRS | To table NPRR240. | Passed |
07/22/2010 | PRS | To recommend approval of NPRR240 as amended by the 7/21/10 WMS comments and as revised by PRS. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | May 25, 2010 |
Sponsor: | Potomac Economics |
Urgent: | No |
Sections: | 6.5.7.3 |
Description: | This Nodal Protocol Revision Request (NPRR) states that the Entity with decision making authority over how a Resource or Split Generation Resource is offered or scheduled shall be responsible for all offers associated with each Resource, including offers represented by a proxy Energy Offer Curve. Additional non-substantive administrative revisions, such as correcting acronym usage, are shown with the author "ERCOT Market Rules." |
Reason: | Clarification of responsibility and accountability for energy offers. |