NPRR242
Summary
Title
Synchronization of Nodal Protocols with PRR792
Next Group
Next Step
Status
Approved on 08/17/2010
Effective Dates
12/01/2010
or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (09/01/10 Nodal Protocols Library)
Voting Record
Date
Gov Body
Motion
Result
08/16/2010
BOARD
To approve NPRR242 as amended by the 8/9/10 ERCOT comments
Passed
08/17/2010
BOARD
To approve NPRR242 as recommended by TAC in the 8/5/10 TAC Report.
Passed
08/05/2010
TAC
To recommend approval of NPRR242 as recommended by PRS in the 7/22/10 PRS Report.
Passed
06/17/2010
PRS
To recommend approval of NPRR242 as submitted.
Passed
07/22/2010
PRS
To endorse and forward the 6/17/10 PRS Report and the Impact Analysis for NPRR242 to TAC.
Background
Status:
Approved
Date Posted:
Jun 1, 2010
Sponsor:
ERCOT
Urgent:
No
Sections:
1.3.1.1, 14.2, 14.5.2, 14.5.3 (new), 14.9.3.1, 14.9.5
Description:
This Nodal Protocol Revision Request (NPRR) synchronizes the Nodal Protocols with Protocol Revision Request (PRR) 792, Revised Renewable Portfolio Standards Allocation Process, Pursuant to P.U.C. Subst. R. 25.173, approved by the ERCOT Board on January 20, 2009.
Reason:
To synchronize the Nodal Protocols with PRR792.