MIS LOG IN

NPRR251

Summary

Title Synchronization of PRR845, Definition for IDR Meters and Optional Removal of IDR Meters at a Premise Where an Advanced Meter Can be Provisioned
Next Group
Next Step
Status Approved on 09/21/2010
Effective Dates
12/09/2011

Sections 18.6.1 and 18.6.2

12/01/2010

All sections except for Sections 18.6.1 and 18.6.2

Action

Date Gov Body Action Taken Next Steps
09/21/2010 BOARD Approved
09/02/2010 TAC Recommended for Approval ERCOT Board for consideration.
08/19/2010 PRS Recommended for Approval TAC for consideration.
07/22/2010 PRS Recommended for Approval PRS for Impact Analysis Review.

Voting Record

Date Gov Body Motion Result
09/21/2010 BOARD To approved NPRR251 as recommended by TAC in the 9/2/10 TAC Report. Passed
09/02/2010 TAC To recommend approval of NPRR251 as recommended by PRS in the 8/19/10 PRS Report with a recommended priority of High for the proposed grey-box language. Passed
08/19/2010 PRS To endorse and forward the 7/22/10 PRS Report with a recommended priority of High for the proposed grey-box language and Impact Analysis for NPRR251 to TAC. Passed
07/22/2010 PRS To recommend approval of NPRR251 as submitted with a recommended priority of High for the proposed grey-box language. Passed

Background

Status: Approved
Date Posted: Jul 7, 2010
Sponsor: Terry Bates on behalf of the Retail Metering Working Group
Urgent: No
Sections: 2.1, 3.14.3, 8.1.3.1, 9.5.6, 9.5.8, 9.5.9, 9.18, 10.2.2, 10.3.2.3, 10.3.3.3, 10.9, 10.9.1, 10.9.2, 10.9.3, 11.4.3.1, 18.6, 18.6.1, 18.6.2, 18.6.3, 18.6.5, 18.6.6
Description: This Nodal Protocol Revision Request (NPRR) synchronizes the Nodal Protocols with Protocol Revision Request (PRR) 845, Definition for IDR Meters and Optional Removal of IDR Meters at a Premise Where an Advanced Meter Can be Provisioned, which clarifies the meaning of an Interval Data Recorder (IDR) Meter and provides for optional removal of IDR Meters under certain conditions for Premises where an Advanced Meter can be provisioned by the Transmission and/or Distribution Service Provider (TDSP). This NPRR also inserts grey boxed language for reporting requirements in Sections 18.6.1 and 18.6.2, to be implemented post Texas Nodal Market Implementation Date, that were removed from PRR845 due to the impact on Nodal systems and therefore deemed "Not Needed for Go-Live" by the CEO Revision Request Review process.
Reason: To synchronize the Nodal Protocols with PRR845. This NPRR provides guidelines for the mandatory installation and removal of an IDR Meter as it relates to the use of provisioned Advanced Meters.