MIS LOG IN

NPRR271

Summary

Title Synchronization to PRR850, Weather Responsiveness Determination for Interval Data Recorders
Next Group
Next Step
Status Approved on 11/16/2010
Effective Dates
12/01/2010

Action

Date Gov Body Action Taken Next Steps
11/16/2010 BOARD Approved
11/04/2010 TAC Recommended for Approval Board consideration
10/21/2010 PRS Recommended for Approval TAC consideration
09/23/2010 PRS Recommended for Approval PRS consider the IA

Voting Record

Date Gov Body Motion Result
11/16/2010 BOARD To approve NPRR270 as recommended by TAC in the 11/4/10 TAC Report. Passed
11/04/2010 TAC To recommend approval of NPRR271 as recommended by PRS in the 10/21/10 PRS Report. Passed
10/21/2010 PRS To endorse and forward the 9/23/10 PRS Report and Impact Analysis for NPRR271 to TAC. All Market Segments were present for the vote. Passed
09/23/2010 PRS To recommend approval of NPRR271 as submitted. Passed

Background

Status: Approved
Date Posted: Sep 13, 2010
Sponsor: ERCOT
Urgent: No
Sections: 11.4.3, 11.4.3.1
Description: This Nodal Protocol Revision Request (NPRR) aligns the Nodal Protocols with zonal Protocols by adding language that limits the applicability of the weather responsiveness test to Interval Data Recorder (IDR) Meters.
Reason: The reason for this revision is to synch the Nodal Protocols with the zonal Protocols. Zonal Protocols were revised to eliminate the weather responsiveness test on Electric Service Identifiers (ESI IDs) with Advanced Meters. Performing the weather responsiveness test on Advanced Meters has a significant impact on ERCOT System processing times.