NPRR276
Summary
Title |
MIS Posting Requirement for the Network Operations Model Load Schedule |
Next Group |
|
Next Step |
|
Status |
Approved on 11/16/2010 |
Effective Dates |
|
Voting Record
Date |
Gov Body |
Motion |
Result |
11/16/2010
|
BOARD |
To approve NPRR276 as recommended by TAC in the 11/4/10 TAC Report. |
Passed |
11/04/2010
|
TAC |
To recommend approval of NPRR276 as recommended by PRS in the 10/21/10 PRS Report |
Passed |
10/21/2010
|
PRS |
To endorse and forward the 9/23/10 PRS Report and Impact Analysis for NPRR276 to TAC |
Passed |
09/23/2010
|
PRS |
To recommend approval of NPRR276 as submitted |
Passed |
Background
Status: |
Approved |
Date Posted: |
Sep 16, 2010
|
Sponsor: |
ERCOT |
Urgent: |
No |
Sections: |
3.10.1 |
Description: |
This Nodal Protocol Revision Request adds a Market Information System (MIS) Public Area posting requirement for the database load schedule. |
Reason: |
Information needs to be made available on the MIS Public Area. |