NPRR295

Summary

Title Synchronization of Protocol for Generation Resource Designation as Mothballed or Decommissioned
Next Group
Next Step
Status Approved on 12/14/2010
Effective Dates
12/14/2010

Action

Date Gov Body Action Taken Next Steps
12/14/2010 BOARD Approved
12/06/2010 TAC Recommended for Approval BOD consideration
11/18/2010 PRS Recommended for Approval TAC consideration

Voting Record

Date Gov Body Motion Result
12/14/2010 BOARD To approve NPRR295 as recommended by tac in the 12/6/10 tac report with an effective date of "upon ercot board approval Passed
12/06/2010 TAC To recommend approval of NPRR295 as recommended by PRS in the 11/18/10 PRS Report, to grant NPRR295 Urgent status, and to direct WMS to review the issues set forth in the 12/3/10 Topaz Power comments Passed
11/18/2010 PRS To recommend approval of NPRR295 as submitted and to forward NPRR295 and the Impact Analysis to TAC. Passed

Background

Status: Approved
Date Posted: Nov 11, 2010
Sponsor: ERCOT
Urgent: Yes
Sections: 2.1, 3.14.1.9, 22, Attachment H:
Description: This Nodal Protocol Revision Request (NPRR) synchronizes the Nodal Protocols with zonal Protocol Section 6.5.9.3, Generation Resource Return to Service Updates, regarding return-to-service of Mothballed or Decommissioned Generation Resources. In addition, a clarification was made for removal of Decommissioned Generation Resources from ERCOT registration systems.
Reason: Language in Section 3.14.1.9, specifying the treatment of Mothballed or Decommissioned Generation Resources, is insufficient in the Nodal Protocols and does not align with current zonal requirements.