Summary

Title Add Administrative NPRR Process to Nodal Protocols
Next Group
Next Step
Status Approved on 03/22/2011
Effective Dates
04/01/2011

Action

Date Gov Body Action Taken Next Steps
03/22/2011 BOARD Approved
02/03/2011 TAC Recommended for Approval ERCOT Board consideration of NPRR297
01/20/2011 PRS Recommended for Approval TAC consideration of NPRR297
12/16/2010 PRS Recommended for Approval PRS Impact Analysis review

Voting Record

Date Gov Body Motion Result
03/22/2011 BOARD To approve NPRR297 as recommended by TAC in the 2/3/11 TAC Report. Passed
02/03/2011 TAC To recommend approval of NPRR297 as recommended by PRS in the 1/20/11 PRS Report. Passed
01/20/2011 PRS To endorse and forward the 12/16/10 PRS Report and Impact Analysis for NPRR297 to TAC. Passed
12/16/2010 PRS To recommend approval of NPRR297 as submitted. Passed

Background

Status: Approved
Date Posted: Nov 23, 2010
Sponsor: ERCOT
Urgent: No
Sections: 21.1, 21.6
Description: This Nodal Protocol Revision Request (NPRR) adds a process for "Administrative NPRRs" to the Nodal Protocols modeled on the similar process for administrative market guide revisions contained in each of the market guides.
Reason: Minor, non-substantive changes to the Nodal Protocols should be permitted without full stakeholder process review. This will save time and resources.