MIS LOG IN

NPRR365

Summary

Title Change in Resource Outage Approvals from Eight to 45 Days (formerly "Change in Resource Outage Approvals from Eight to 90 Days")
Next Group
Next Step
Status Approved on 09/20/2011
Effective Dates
11/02/2012

Action

Date Gov Body Action Taken Next Steps
09/20/2011 BOARD Approved
09/01/2011 TAC Recommended for Approval TAC Consideration of priority and rank
08/18/2011 PRS Recommended for Approval TAC Consideration
05/19/2011 PRS Deferred/Tabled PRS Language Consideration

Voting Record

Date Gov Body Motion Result
09/20/2011 BOARD To approve NPRR365 as recommended by TAC in the 9/1/11 TAC Report Passed
09/01/2011 TAC To recommend approval of NPRR365 as recommended by PRS in the 8/18/11 PRS Report and as revised by TAC via roll call vote. Passed
08/18/2011 PRS To recommend approval of NPRR365 as amended by the 8/12/11 ROS comments and as revised by PRS and to forward NPRR365 to TAC Passed
05/19/2011 PRS To table NPRR365 Passed

Background

Status: Approved
Date Posted: May 4, 2011
Sponsor: ERCOT
Urgent: Yes
Sections: 3.1.1, 3.1.4.4, 3.1.6, 3.1.6.4, 3.1.6.5, 3.1.6.6, 3.1.6.8, 3.1.6.9, 3.1.6.10
Description: Consistent with Recommendation 6B of the March 15, 2011, Report of the Rotating Blackout Operations Task Force of the ERCOT Board, this Nodal Protocol Revision Request (NPRR) revises the deadline for ERCOT approval of Resource Outages from an eight-day notice to a 45-day notice while aligning the new Resource Outage timelines to match those of Transmission Outages.
Reason: This NPRR gives ERCOT the ability to coordinate Resource Outages received with less than a 45-day notice with Transmission Outages. This NPRR also proposes to more clearly define ERCOT’s requirements for withdrawing approval (or acceptance) of Resource Outages if reliability of the ERCOT System is at risk.

Key Documents

Related Content