NPRR408
Summary
Title | Clarification of ERCOT Authority to Deny Energization of Non-Compliant Generators |
---|---|
Next Group | |
Next Step | |
Status | Approved on 02/21/2012 |
Effective Dates |
03/01/2012
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
02/21/2012 | BOARD | Approved | |
01/05/2012 | TAC | Recommended for Approval | Board consideration |
12/01/2011 | TAC | Deferred/Tabled | TAC consideration |
11/17/2011 | PRS | Recommended for Approval | TAC consideration |
10/20/2011 | PRS | Recommended for Approval | PRS review the Impact Analysis |
09/22/2011 | PRS | Deferred/Tabled | PRS consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
02/21/2012 | BOARD | To approve NPRR408 as recommended by TAC in the 1/5/12 TAC Report. | Passed |
01/05/2012 | TAC | To recommend approval of NPRR408 as recommended by PRS in the 11/17/11 PRS Report. | Passed |
12/01/2011 | TAC | To table NPRR408 for one month | Passed |
11/17/2011 | PRS | To endorse and forward the 10/20/11 PRS Report as revised by PRS and Impact Analysis for NPRR408 to TAC. | Passed |
10/20/2011 | PRS | To recommend approval of NPRR408 as amended by the 10/19/11 Topaz comments. | Passed |
09/22/2011 | PRS | To table NPRR408 | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Sep 6, 2011 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 1.6.5, 16.5 |
Description: | This Nodal Protocol Revision Request (NPRR) clarifies ERCOT’s authority to deny energization of a new or materially changed All-Inclusive Generation Resource if ERCOT determines the Resource Entity cannot demonstrate that the Resource would be able to comply with technical standards in the Protocols, the Planning Guide, the Nodal Operating Guides, and Other Binding Documents. |
Reason: | New or modified All-Inclusive Generation Resources interconnecting with the ERCOT System have sometimes failed to comply with technical standards in the Protocols and Other Binding Documents. These failures may create problems that either cannot be remedied after Resource energization or cannot be remedied without creating significant reliability issues or imposing substantial costs on Market Participants and/or consumers. |
Key Documents
Sep 6, 2011 - doc - 69.5 KB
Sep 6, 2011 - doc - 54.5 KB
Sep 8, 2011 - doc - 55 KB
Sep 15, 2011 - doc - 57 KB
Sep 16, 2011 - doc - 38.5 KB
Sep 26, 2011 - doc - 76.5 KB
Oct 4, 2011 - doc - 62 KB
Oct 4, 2011 - doc - 63.5 KB
Oct 5, 2011 - doc - 65.5 KB
Oct 17, 2011 - doc - 37.5 KB
Oct 17, 2011 - doc - 66.5 KB
Oct 19, 2011 - doc - 67.5 KB
Oct 24, 2011 - doc - 91.5 KB
Jan 3, 2012 - doc - 91 KB
Nov 23, 2011 - doc - 55.5 KB
Jan 3, 2012 - doc - 93.5 KB
Jan 9, 2012 - doc - 95.5 KB
Feb 21, 2012 - doc - 96 KB