Summary
Title | Requirements for Energy Offer Curves in the Real Time SCED for Generation Resources Committed in RUC |
---|---|
Next Group | |
Next Step | |
Status | Approved on 02/21/2012 |
Effective Dates |
03/01/2012
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
02/21/2012 | BOARD | Approved | |
02/02/2012 | TAC | Recommended for Approval | ERCOT Board consideration of NPRR435 |
01/19/2012 | PRS | Recommended for Approval | TAC consideration of NPRR435 |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
02/21/2012 | BOARD | To approve NPRR435 as recommended by TAC in the 2/2/12 TAC Report. | Passed |
02/02/2012 | TAC | To recommend approval of NPRR435 as recommended by PRS in the 1/19/12 PRS Report and as revised by TAC. | Passed |
01/19/2012 | PRS | To recommend approval of NPRR435 as amended by the 1/10/12 Luminant-Exelon comments and as revised by PRS and to forward NPRR435 and the Impact Analysis to TAC. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Jan 3, 2012 |
Sponsor: | ERCOT |
Urgent: | Yes |
Sections: | 6.4.3.1 (new) |
Description: | This Nodal Protocol Revision Request (NPRR) adds a requirement for the Qualified Scheduling Entity (QSE) of a Generation Resource committed by the Reliability Unit Commitment (RUC) process to submit an Energy Offer Curve that prices all energy from Low Sustained Limit (LSL) to High Sustained Limit (HSL) at the System-Wide Offer Cap (SWCAP) for RUC committed intervals. When Generation Resources are committed in the Day Ahead or during the Adjustment Period in the RUC process, the QSE shall submit an Energy Offer Curve for the Generation Resource that meets the above requirements no later than the end of the Adjustment Period immediately preceding the Operating Period that includes an Operating Hour coincident with the first hour of the RUC Dispatch Instruction. QSE updates to an Energy Offer Curve entered at the end of the Adjustment Period become effective in ERCOT systems at the start of the next Operating Period. Therefore, if a Generation Resource is committed by an ERCOT Operator issued Verbal Dispatch Instruction(VDI) for the Operating Hour in the immediate Operating Period, then it is expected that the QSE shall submit an Energy Offer Curve that meets the requirements described above as soon as reasonably practicable after receipt of the VDI. ERCOT systems will not validate that the Energy Offer Curve for RUC-committed Generation Resources meet the requirements described above. QSEs are solely responsible to make the submission changes needed to implement the Protocol requirements described in this NPRR. |
Reason: | To address concerns raised at the December 8, 2011 Public Utility Commission of Texas (PUCT) Open Meeting regarding Project No. 37897, PUC Proceeding Relating to Resource and Reserve Adequacy and Shortage Pricing. |
Key Documents
Jan 3, 2012 - doc - 60 KB
Jan 3, 2012 - doc - 54 KB
Jan 9, 2012 - doc - 41 KB
Jan 10, 2012 - doc - 45.5 KB
Jan 12, 2012 - doc - 41 KB
Jan 12, 2012 - xls - 103 KB
Jan 17, 2012 - doc - 52.5 KB
Jan 24, 2012 - doc - 69 KB
Jan 26, 2012 - doc - 38.5 KB
Jan 31, 2012 - doc - 141 KB
Feb 3, 2012 - doc - 76 KB
Feb 3, 2012 - xls - 131.5 KB
Feb 21, 2012 - doc - 77 KB