NPRR440

Summary

Title Consideration of Generation Availability in RMR Analyses
Next Group
Next Step
Status Rejected on 03/22/2012

Action

Date Gov Body Action Taken Next Steps
03/22/2012 PRS Rejected
02/23/2012 PRS Deferred/Tabled PRS for consideration.

Voting Record

Date Gov Body Motion Result
03/22/2012 PRS To to recommend approval of NPRR440 as amended by the 2/16/12 Luminant Energy Company comments Failed
02/23/2012 PRS To table NPRR440 and refer the issue to ROS. Passed

Background

Status: Rejected
Date Posted: Jan 30, 2012
Sponsor: Paul Rocha on behalf of CenterPoint Energy
Urgent: No
Sections: 3.14.1, 3.14.1.2
Description: The Nodal Protocol Revision Request (NPRR) modifies provisions that relate to Reliability Must-Run (RMR) analysis to ensure generation availability is assessed by ERCOT in RMR evaluations over at least a five year planning horizon.
Reason: The revisions proposed by this NPRR are necessary to ensure that sufficient Generation Resources are available in transmission-constrained areas to reliably manage constraints over at least a five year planning horizon.