MIS LOG IN

NPRR479

Summary

Title Daily Net Outage MW
Next Group
Next Step
Status Approved on 12/11/2012
Effective Dates
10/21/2013

Action

Date Gov Body Action Taken Next Steps
12/11/2012 BOARD Approved
11/01/2012 TAC Recommended for Approval ERCOT Board consideration of NPRR479
10/18/2012 PRS Recommended for Approval TAC consideration of NPRR479
09/20/2012 PRS Recommended for Approval PRS Impact Analysis review

Voting Record

Date Gov Body Motion Result
12/11/2012 BOARD To approve NPRR479 as recommended by TAC in the 11/1/12 TAC Report. Passed
11/01/2012 TAC To recommend approval of NPRR479 as recommended by PRS in the 10/18/12 PRS Report. Passed
10/18/2012 PRS To endorse and forward the 9/20/12 PRS Report as amended by the 10/15/12 ERCOT comments and Impact Analysis for NPRR479 to TAC with a recommended priority of 2013 and rank of 795. Passed
09/20/2012 PRS To recommend approval of NPRR479 as amended by the 9/13/12 WMS comments and as revised by PRS. Passed

Background

Status: Approved
Date Posted: Aug 21, 2012
Sponsor: Mercuria Energy
Urgent: No
Sections: 3.2.3, 4.2.3.1
Description: This Nodal Protocol Revision Request (NPRR) modifies the information provided by ERCOT to Market Participants regarding net daily Outage MWs.
Reason: This NPRR will provide a needed increase in data transparency regarding Outage MWs in a manner that enhances data transparency and market efficiency without releasing Resource-specific information.

Key Documents

Related Content