MIS LOG IN

NPRR522

Summary

Title Adjustment of Demand Response Performance for Distribution Losses (formerly "Adjustment of Demand Response Performance for T&D Losses ")
Next Group
Next Step
Status Approved on 07/16/2013
Effective Dates
08/01/2013

All sections except for Section 3.14.3.3(3)(a)

10/01/2013

Section 3.14.3.3(3)(a)

Action

Date Gov Body Action Taken Next Steps
07/16/2013 BOARD Approved
06/06/2013 TAC Recommended for Approval ERCOT Board Consideration
05/16/2013 PRS Recommended for Approval
04/18/2013 PRS Recommended for Approval PRS IA Review
03/21/2013 PRS Recommended for Approval PRS IA Review

Voting Record

Date Gov Body Motion Result
07/16/2013 BOARD To approve NRR522 as recommended by TAC in the 6/6/13 TAC Report Passed
06/06/2013 TAC To recommend approval of NPRR522 as recommended by PRS in the 5/16/13 PRS Report Passed
05/16/2013 PRS To endorse and forward the 4/18/13 PRS Report and Impact Analysis for NPRR522 to TAC Passed
04/18/2013 PRS To recommend approval of NPRR522 as amended by the 4/18/13 CPS Energy comments and as revised by PRS Passed
03/21/2013 PRS To recommend approval of NPRR522 as amended by the 3/14/13 DSWG comments and as revised by PRS Passed

Background

Status: Approved
Date Posted: Feb 25, 2013
Sponsor: DSWG
Urgent: No
Sections: 3.7.1.2, 3.9.1, 3.14.3.3, 4.4.7.2.1, 8.1.1.2, 13.3
Description: This Nodal Protocol Revision Request (NPRR) addresses inequality by adjusting the metered Load of demand response Resources for Distribution Losses.
Reason: This NPRR would adjust the quantity of demand response that can be offered into Ancillary Services and Emergency Response Services (ERS) to include an adjustment for line losses.

Key Documents

Related Content