NPRR522
Summary
Title | Adjustment of Demand Response Performance for Distribution Losses (formerly "Adjustment of Demand Response Performance for T&D Losses ") |
---|---|
Next Group | |
Next Step | |
Status | Approved on 07/16/2013 |
Effective Dates |
08/01/2013
All sections except for Section 3.14.3.3(3)(a) 10/01/2013
Section 3.14.3.3(3)(a) |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
07/16/2013 | BOARD | Approved | |
06/06/2013 | TAC | Recommended for Approval | ERCOT Board Consideration |
05/16/2013 | PRS | Recommended for Approval | |
04/18/2013 | PRS | Recommended for Approval | PRS IA Review |
03/21/2013 | PRS | Recommended for Approval | PRS IA Review |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
07/16/2013 | BOARD | To approve NRR522 as recommended by TAC in the 6/6/13 TAC Report | Passed |
06/06/2013 | TAC | To recommend approval of NPRR522 as recommended by PRS in the 5/16/13 PRS Report | Passed |
05/16/2013 | PRS | To endorse and forward the 4/18/13 PRS Report and Impact Analysis for NPRR522 to TAC | Passed |
04/18/2013 | PRS | To recommend approval of NPRR522 as amended by the 4/18/13 CPS Energy comments and as revised by PRS | Passed |
03/21/2013 | PRS | To recommend approval of NPRR522 as amended by the 3/14/13 DSWG comments and as revised by PRS | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Feb 25, 2013 |
Sponsor: | DSWG |
Urgent: | No |
Sections: | 3.7.1.2, 3.9.1, 3.14.3.3, 4.4.7.2.1, 8.1.1.2, 13.3 |
Description: | This Nodal Protocol Revision Request (NPRR) addresses inequality by adjusting the metered Load of demand response Resources for Distribution Losses. |
Reason: | This NPRR would adjust the quantity of demand response that can be offered into Ancillary Services and Emergency Response Services (ERS) to include an adjustment for line losses. |