NPRR527
Summary
Title | Required Combined Cycle Telemetry for Operational Awareness and PDCWG Analysis |
---|---|
Next Group | |
Next Step | |
Status | Approved on 11/19/2013 |
Effective Dates |
12/01/2013
All sections except for Section 6.5.5.2(2)(j) 11/01/2014
Section 6.5.5.2(2)(j) |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
11/19/2013 | BOARD | Approved | |
09/05/2013 | TAC | Recommended for Approval | ERCOT Board Consideration |
08/22/2013 | PRS | Recommended for Approval | TAC Consideration |
07/18/2013 | PRS | Recommended for Approval | PRS IA Review |
03/21/2013 | PRS | Deferred/Tabled | PRS Language Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
11/19/2013 | BOARD | To approve NPRR527 as recommended by TAC in the 9/5/13 TAC Report. | Passed |
09/05/2013 | TAC | To recommend approval of NPRR527 as recommended by PRS in the 8/22/13 PRS Report | Passed |
08/22/2013 | PRS | To endorse and forward the 7/18/13 PRS Report and Impact Analysis to TAC with a recommended priority of 2014 and rank of 990 | Passed |
07/18/2013 | PRS | To recommend approval of NPRR527 as amended by the 6/20/13 PDCWG comments and as revised by PRS | Passed |
03/21/2013 | PRS | To table NPRR527 and forward the issue to ROS and WMS to review in conjunction with NPRR524, Resource Limits in Providing Ancillary Service | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Mar 6, 2013 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 2.1, 2.2, 6.5.5.2 |
Description: | This Nodal Protocol Revision Request (NPRR) requires Combined Cycle Generation Resources to telemeter individual High Sustainable Limits (HSLs) for gas and steam turbines. The HSLs for combustion and steam turbines were previously submitted in the zonal market and ERCOT requests this practice be resumed in the Nodal market. |
Reason: | This NPRR allows the Performance, Disturbance, Compliance Working Group (PDCWG) to accurately measure the Primary Frequency Response of individual components of Combined Cycle Generation Resources while using ERCOT collected data necessary to analyze each Measurable Event. Revisions to the ERCOT Nodal ICCP Communications Handbook will be required as a result of this NPRR. The Qualified Scheduling Entity (QSE) Managers Working Group (QMWG) and the PDCWG unanimously agreed that this telemetry needs to be submitted to ERCOT at their 11/28/12 joint meeting. However, in subsequent discussion and vetting of the NPRR in PDCWG meetings, member consensus has developed on the need to have a total Non-Frequency Responsive Capacity (NFRC) value for each Combined Cycle Generation Resource in operation instead of a value of NFRC for each combustion turbine and steam turbine generator component. |