Summary
Title | Seasonal Generation Notifications |
---|---|
Next Group | |
Next Step | |
Status | Approved on 12/10/2013 |
Effective Dates |
01/01/2014
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
12/10/2013 | BOARD | Approved | |
11/07/2013 | TAC | Recommended for Approval | ERCOT Board for consideration. |
10/17/2013 | PRS | Recommended for Approval | TAC for consideration. |
09/19/2013 | PRS | Recommended for Approval | PRS for Impact Analysis review. |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
12/10/2013 | BOARD | To approve NPRR565 as recommended by TAC in the 11/7/13 TAC Report. | Passed |
11/07/2013 | TAC | To recommend approval of NPRR565 as recommended by PRS in the 10/17/13 PRS Report. | Passed |
10/17/2013 | PRS | To endorse and forward the 9/19/13 PRS Report and the Impact Analysis for NPRR565 to TAC. | Passed |
09/19/2013 | PRS | To recommend approval of NPRR565 as submitted. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Aug 23, 2013 |
Sponsor: | Luminant Energy Company, LLC |
Urgent: | No |
Sections: | 3.14.1.2, 3.14.1.9 |
Description: | This Nodal Protocol Revision Request (NPRR) proposes that a seasonally operating Resource Entity’s 15 day Notification requirement (when returning to service early, or suspending operations later) be based on the Seasonal Operation Period designated by the Resource Entity in its Notification of Suspension of Operations. Additional revisions correct references to Part III of Section 22, Attachment E, Notification of Suspension of Operations. |
Reason: | The current Protocols require Notification if a seasonally operating Resource Entity plans to return to service on dates other than June 1 or continue operating past September 30. This NPRR proposes that a Resource Entity would only need to provide the 15 day Notification if it intends to begin or suspend its Seasonal Operation Period on a date other than the date designated by the Resource Entity in its Notification of Suspension of Operations. Additional revisions are proposed to correct references to Part III of Section 22, Attachment E, that were not included in NPRR514, Seasonal Generation Resource. |
Key Documents
Aug 23, 2013 - doc - 77 KB
Sep 24, 2013 - doc - 82.5 KB
Oct 9, 2013 - doc - 55 KB
Oct 22, 2013 - doc - 82 KB
Nov 8, 2013 - doc - 84.5 KB
Dec 10, 2013 - doc - 85.5 KB