Title Clarification of Administrative Pricing Requirements for Self-Committed Combined Cycle Combustion Turbines on a Resource Committed by RUC
Next Group
Next Step
Status Withdrawn

Action

Date Gov Body Action Taken Next Steps
01/16/2014 PRS Deferred/Tabled PRS language consideration

Voting Record

Date Gov Body Motion Result
01/16/2014 PRS To table NPRR585 and refer the issue to WMS. Passed

Background

Status: Withdrawn
Date Posted: Dec 10, 2013
Sponsor: Calpine
Urgent: No
Sections: 6.4.3.1
Description: This Nodal Protocol Revision Request (NPRR) clarifies that for Qualified Scheduling Entities (QSEs) managing Combined Cycle Trains, self-commitment of combustion turbines, in addition to a configuration committed by Reliability Unit Commitment (RUC), may be priced at values other than the System-Wide Offer Cap (SWCAP) and should precede RUC-committed MW in merit order on the Energy Offer Curve for the entire Combined Cycle Train.
Reason: The current language in Section 6.4.3.1 does not address the requirements of administrative pricing for self-committed combustion turbines in addition to a RUC-committed configuration.