MIS LOG IN

NPRR588

Summary

Title Clarifications for PV Generation Resources
Next Group
Next Step
Status Approved on 06/10/2014
Effective Dates
12/10/2015

Sections 2.1 (partial) and 3.10.7.2(11)

02/10/2016

All remaining sections

Action

Date Gov Body Action Taken Next Steps
06/10/2014 BOARD Approved
04/24/2014 TAC Recommended for Approval ERCOT Board for consideration
04/10/2014 PRS Recommended for Approval TAC for consideration
03/18/2014 PRS Deferred/Tabled PRS for IA review
02/13/2014 PRS Recommended for Approval PRS Impact Analysis review
01/16/2014 PRS Deferred/Tabled PRS language consideration

Voting Record

Date Gov Body Motion Result
06/10/2014 BOARD To approve NPRR588 as recommended by TAC in the 4/24/14 TAC Report Passed
04/24/2014 TAC To recommend approval of NPRR588 as recommended by PRS in the 4/10/14 PRS Report. Passed
04/10/2014 PRS To endorse and forward the 3/18/14 PRS Report and Impact Analysis for NPRR588 to TAC with a recommended priority of 2014 and a rank of 1130 Passed
03/18/2014 PRS To table for one month Passed
02/13/2014 PRS To recommend approval of NPRR588 as amended by the 2/6/14 WMS comments. Passed
01/16/2014 PRS To table NPRR588 and refer the issue to WMS. Passed

Background

Status: Approved
Date Posted: Dec 17, 2013
Sponsor: ETWG
Urgent: No
Sections: 2.1, 2.2, 3.2.5, 3.2.6.2.2, 3.9.1, 3.10.7.2, 3.15, 4.4.9.2.3, 4.4.9.4.2, 6.5.5.2, 7.9.1.3, 8.1.1.2, 8.1.1.4.1, 14.2.1
Description: This Nodal Protocol Revision Request (NPRR) creates a definition of PhotoVoltaic Generation Resource (PVGR), and clarifies the treatment of such Resources within these Protocols
Reason: While over 1.6 GW of PVGRs are presently at various stages within the interconnection queue, there remains a lack of specificity regarding the treatment of such Resources, when compared to other Resources that are defined in the Protocols.

Key Documents

Related Content