Summary

Title PVGR Forecasting
Next Group
Next Step
Status Approved on 08/12/2014
Effective Dates
12/10/2015

Sections 2.1 and 4.2.3

02/10/2016

All remaining sections

Action

Date Gov Body Action Taken Next Steps
08/12/2014 BOARD Approved
07/31/2014 TAC Recommended for Approval ERCOT Board for consideration
07/17/2014 PRS Recommended for Approval TAC for consideration
06/11/2014 PRS Recommended for Approval PRS for Impact Analysis review
05/15/2014 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
08/12/2014 BOARD To approve NPRR615 as recommended by TAC in the 07/31/14 TAC Report Passed
07/31/2014 TAC To recommend approval as recommended by PRS in the 7/17/14 PRS Report Passed
07/17/2014 PRS To endorse and forward to 6/11/14 PRS Report and Impact Analysis to TAC Passed
06/11/2014 PRS To recommend approval as amended by the 6/6/14 WMS comments Passed
05/15/2014 PRS To table and refer the issue to WMS Passed

Background

Status: Approved
Date Posted: Apr 16, 2014
Sponsor: ETWG
Urgent: No
Sections: 2.1, 2.2, 3.9.1, 3.13, 4.2.3, 5.7.4, 5.7.4.1.1, 6.3.1
Description: This NPRR establishes a definition for Short-Term PhotoVoltaic Power Forecast (STPPF) and clarifies the use of the resulting forecast within the Protocols. It is requested that WMS recommend a value for X in Section 4.2.3.
Reason: Addresses current operational issues; adds market efficiencies and enhancements; and incorporates Photovoltaic power forecasts into system operations