NPRR626
Summary
Title | Reliability Deployment Price Adder (formerly "ORDC Price Reversal Mitigation Enhancements") |
---|---|
Next Group | |
Next Step | |
Status | Approved on 08/12/2014 |
Effective Dates |
10/01/2014
Section 6.4.4.1 06/25/2015
All remaining sections |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
08/12/2014 | BOARD | Approved | |
07/31/2014 | TAC | Recommended for Approval | ERCOT Board for consideration |
07/17/2014 | PRS | Recommended for Approval | TAC for consideration. |
06/11/2014 | PRS | Recommended for Approval | PRS for Impact Analysis review |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
08/12/2014 | BOARD | To approve NPRR626 as recommended by TAC in the 7/31/14 TAC Report. | Passed |
07/31/2014 | TAC | To recommend approval of NPRR626 as recommended by PRS in the 7/17/14 PRS Report and as revised by TAC. | Passed |
07/17/2014 | PRS | To endorse and forward the 6/11/14 PRS Report as amended by the 7/16/14 ERCOT comments and the Impact Analysis for NPRR626 to TAC. | Passed |
06/11/2014 | PRS | To recommend approval of NPRR626 as amended by the 6/10/14 ERCOT comments and as revised by PRS and to bring the Impact Analysis back to PRS for review. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | May 16, 2014 |
Sponsor: | Luminant Energy Company, LLC |
Urgent: | Yes |
Sections: | 2.1, 3.5.2.1, 3.5.2.2, 3.5.2.3, 3.5.2.4, 3.5.2.5, 3.5.2.6, 6.3, 6.3.2, 6.5.7.3, 6.5.7.3.1, 6.5.9.2, 6.6.1, 6.6.1.1, 6.6.1.2, 6.6.3.1, 6.7.4 |
Description: | Intends to mitigate the price reversal/suppression associated with the deployment of Load Resources and/or other out-of-market reliability deployments that may inappropriately reduce the total Real-Time price in times of scarcity. |
Reason: | Addresses current operational issues, and Market efficiencies or enhancements |